GAZETTE NOTICE NO. 7108
GAZETTE NOTICE NO. 7108
THE ENVIRONMENTAL MANAGEMENT AND , CO-ORDINATION ACT
(No. 8 of 1999)
REGULATION
PURSUANT to Regulation 21 of the Environmental Management
and Co-ordination (Impact Assessment and Audit) Regulations, 2003,
the National Environment Management Authority (NEMA) has
received an Environmental Impact Assessment Study Report for the
above proposed project.
The proponent, Seascan Energy Limited, proposes to construct a
42000 MT total storage capacity, six (6) mounds each having 4 tanks
of 7000 MT capacity LPG storage and filling plant, truck loading
gantries of 20 trucks capacity at a time, 300 mm diameter LPG
pipeline from KOT to the site through KPRL way leave approximately
15kms, rail siding for LPG wagons loading, firefighting system,
administration block, driveway and truck parking facilities, green
areas, associated facilities and amenities on Plot No. 3430, Mombasa
County.
The following are the anticipated impacts and proposed mitigation
measures:
Possible Impacts Mitigation Measures
Vegetation • Maintain native mangrove cover by
removal/clearance selective removal of trees which cannot
be incorporated in the project design by
use of manual clearing technics.
• Design of appropriate construction that
provides for incorporation of existing
mangrove vegetation.
Generation of solid • Contractor to provide strategically
waste located solid waste collection container
(skips).
• Transport and dispose all waste away
from site.
Possible Impacts Mitigation Measures
• No burning of materials is to be
permitted at the site.
• Sensitization of Workers on Fire Safety
Risks.
• No burning of any materials near or in
the site.
Potential pollution of • No disposal of domestic waste at the
surface and project site.
groundwater
• Provision of used oil containers at a
central point.
• Use of waste bins/proper wastes
management.
• Pave parking area for trucks and direct
drainage to containment.
• Analysis of water at the site area 2 times
year.
Safety of workers and • Use of construction site barrier tapes to
other visitors to isolate the site(working) area to bar
construction site intruders from accessing the area in case
of a dropping object.
• Appropriate head, hand and foot
protection (PPE) during the manual
clearing of vegetation and construction
activities.
• Adopting ergonomic work flow designs
that fit physical tasks to employees and
not vice versa. Maintain work
productivity.
• Construction site visitors require
appropriate safety Gear.
Possible Impacts Mitigation Measures
arising years of age) to perform any form of
work at the site during construction.
• Contractor will be required to comply
with the Employment Act, 2007.
The full report of the proposed project is available for inspection
during working hours at:
(a) Principal Secretary, Ministry of Environment and Forestry,
NHIF Building, Community, P.O. Box 30126-00100,
Nairobi .
(b) Director-General, NEMA, Popo Road, off Mombasa Road,
P.O. Box 67839-00200, Nairobi.
(c) County Director of Environment, Mombasa County.
A copy of the report can be downloaded at www.nema.go.ke
The National Environment Management Authority invites
members of the public to submit oral or written comments within
thirty (30) days from the date of publication of this notice to the
Director-General, NEMA, to assist the Authority in the decision
making process regarding this project.
Comments can also be emailed to dgnema@nema.go.ke
MAMO B. MAMO,
Director-General,
MR/1791928 National Environment Management Authority.
Dated the 16th July, 2021.
MAMO B. MAMO,
Director-General, National Environment Management Authority.
Extracted Entities (1)
previous_gazette_ref
7108
Details
- Act / Legislation
- THE ENVIRONMENTAL MANAGEMENT AND , CO-ORDINATION ACT
- Reference
- No. 8 of 1999
- Signed By
- MAMO B. MAMO
- Title
- Director-General, National Environment Management Authority
- Date Signed
- 16th July 2021