Back
REGISTRATION
100% confidence
via regex
GAZETTE NOTICE NO. 8787
GAZETTE NOTICE NO. 8787
THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
(No. 8 of 1999)
REGISTRATION
PURSUANT to Regulation 21 of the Environmental Management
and Co-ordination (Impact Assessment and Audit) Regulations, 2003,
the National Environment Management Authority (NEMA) has
received an Environmental Impact Assessment Study Report for the
above proposed project.
The proponent, Blue Regency Investments Limited, proposes to
demolish an existing single dwelling maisonette and construct a total
of 144No. of units in 6 blocks of 12floors each, wastewater treatment
plant, swimming pool, solar installation, vehicle parking, underground
water tanks and associated amenities on plot L.R. 1542/I/MN at Nyali,
Mombasa County.
The following are the anticipated impacts and proposed mitigation
measures:
Possible Impacts Mitigation Measures
Traffic Impact • The timing of the truck arrivals and
departures should be largely outside of
the vehicular peak periods.
• During the demolition and construction
stages, all trucks to enter the construction
site.
• A traffic marshalling to be developed in
unison with contractor during
construction.
• Warning signs to be placed to advise
pedestrians and manage their safety when
walking across the construction
driveways.
• During activity periods of high traffic
volume (such as demolition, excavation
and concrete pours), pedestrians to be
guided walking across the construction
driveways exit by traffic controllers.
• The use of public transport and
carpooling to be actively encouraged.
• Vehicle access to neighbouring properties
and public beach to be unimpaired.
• No machinery or material to be stored on
the footpath or verges or on public areas.
• All materials handling to be done on site.
Construction
waste
• Avoid overloading trucks and cover
trucks to minimize dust and spillages
from trucks during transportation.
• For aggregate and sand, use water sprays
or covered chutes to reduce dust emission
during loading and unloading of
materials.
• Maintain mixing plants in good working
condition so as to reduce emission from
the plant.
• As far as possible, plan truck trips to
material source and to the sites during low
traffic volume.
• Implement safety procedures to reduce
the potential for road accidents.
Noise and
vibration
pollution
• Schedule noisy activities during the
normal working hours of between 8am to
5 p.m. No work should be undertaken at
night or very early in the morning;
• Switch off idle machines and equipment.
• Ensure machinery is well serviced to
reduce noise emitted.
• The contractor should adhere to the
provision in the Environmental
Management and Co-ordination (Noise
and Excessive Vibration pollution)
(control) regulations, 2009.
• Provide workers with appropriate PPEs
when working under noisy environment
e.g. ear plugs.
• Construction waste is not to enter the
biophysical or socio-economic
environment.
4214 4214
Possible Impacts Mitigation Measures
• Contractors to have waste management
plans to mitigate potential impacts.
Air pollution • Practice dust management techniques,
including watering spraying to suppress
dust.
• Move earth and sand in covered
vehicles/transport to avoid it being blown
by wind increasing suspended particulate
matter in the atmosphere.
• All power plants to be of good condition
with acceptable smoke emissions.
• Set up dust barriers/screens at strategic
locations.
• Provide and enforce use of Personal
Protective Equipment (PPE) for staff.
Water shortages • Replace or repair leaking pipes supplying
water to the construction sites to
minimize wastage.
• The Contractor should ensure provision of
adequate water storage facilities on the
construction site to meet project needs
during periods of high demand externally
and refill of storage tanks during periods
of low demand.
• Incorporate water harvesting techniques
and matched storage.
• Waste water treatment and reuse in
landscaping.
• Regularize the existing borehole.
Pollution/contami
nation of ground
and surface
water
• Appropriate containment structures to be
provided to store contaminated water
from the construction site. The contractor
should ensure this water are properly
disposed and not allowed to be drained on
site.
• Concrete batching area should be
bounded to prevent contamination of soils
and surface water features.
• All fuel storage to be appropriately
bunded and provided with a canopy.
• Provision of adequate sanitary facilities
for construction workers to enable proper
disposal of fecal matter and avoid
contamination of surface water features
which could be a cause of water borne
diseases.
Occupational
Health and
Safety
• Contractor should ensure registration of
all construction works by the Director,
Directorate of Occupational Health and
Safety Services (DOHSS) in compliance
with the Buildings and Works of
Construction Engineering Rules, 1984.
• Contractor should contract a qualified
Health and Safety advisor to conduct
training and monitoring of construction
works.
• Contractor should provide a standard First
Aid Kit onsite.
• The Contractor should train several
workers in First Aid depending on the
number of workers on site as stipulated in
the First Aid Rules 1977 through DOSHS
certified First Training institution e.g. Red
Cross, St. John Ambulance.
The full report of the proposed project is available for inspection
during working hours at:
(a) Principal Secretary, Ministry of Environment and Forestry,
NHIF Building, 12th Floor, Ragati Road, Upper Hill, P.O.
Box 30126–00100, Nairobi.
(b) Director-General, NEMA, Popo Road, off Mombasa Road,
P.O. Box 67839–00200, Nairobi.
(c) County Director of Environment, Mombasa County.
A copy of the report can be downloaded at www.nema.go.ke
The National Environment Management Authority invites
members of the public to submit oral or written comments within
thirty (30) days from the date of publication of this notice to the
Director-General, NEMA, to assist the Authority in the decision
making process regarding this project.
Comments can also be emailed to dgnema@nema.go.ke
MAMO B. MAMO,
Director-General,
MR/1801679 National Environment Management Authority.
Dated the 27th August, 2021.
MAMO B. MAMO,
Director-General, National Environment Management Authority.
Extracted Entities (1)
previous_gazette_ref
8787
Details
- Act / Legislation
- THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
- Reference
- No. 8 of 1999
- Signed By
- MAMO B. MAMO
- Title
- Director-General, National Environment Management Authority
- Date Signed
- 27th August 2021
- Page
- 43
- Extraction Method
- regex
Source Gazette
Vol. CXXIII No. 176
Published 16th March 2021