GAZETTE NOTICE NO. 6408

PURSUANT to clause 3 of Part III of the Schedule of Tariffs 2018, notice is given that all prices for electrical energy specified in Part II of the said Schedule will be liable to an inflation adjustment of plus 25 cents per kWh for all meter readings taken in July-December, 2019. Information used to calculate the inflation adjustment: INFA KenGen INFAKPLC INFAIPPs Last Half-year Period Inflation Costs Under/(Over) Recovery Total Escalated Cost 346,185,042.18 601,167,535.81 226,217,120.29 (12,937,358.41) 1,160,632,339.86 Total projected units generated or purchased by the Company in July-December, 2019- (Gp) = 5,514,796,291 kWh ROBERT PAVEL OIMEKE, MR/5815861 Director-General.

Extracted Entities (1)

previous_gazette_ref

6408

Details

Signed By
ROBERT PAVEL OIMEKE
Title
Director-General
Page
26
Extraction Method
regex