GAZETTE NOTICE NO. 3949
PURSUANT to clause 5 of Part HI of the Schedule of Tariffs 2018, notice is given that all prices for electrical energy specified in Part II -(A) of
the said Schedule will be liable to a Water Resource Management Authority (WRMA) levy of plus 2.11 Kenya cents per kWh for all meter readings
to be taken in June, 2020.
Information used to calculate the WRMA Levy:
Approved WRMA levy for energy purchased from hydropower plants of capacity equal to or above 1MW = 5 Kenya cents per KWh.
Units Purchased In May, 2020
Hydropower Plant (KWh.)
Gitaru 82,092 DOO
Kamburu 35,101,000
Kiambere 80,372,000
Kindaruma 16,955,300
Masinga 346,000
Tana 13,513,528
Wanjii -
Sagana 1,017,657
Ndula -
Turkwel 28,889,800
Gogo 360,453
Units Purchased In May, 2020
Hydropower Plant (KWh.)
Sondu Miriu 42,764,000
Sangoro 13,450,300
Regen-Terem 3,057,304
Chania 121,653
Gura 1,027,858
Total units purchased from hydropower plants with capacity equal to or above 1MW = 319,068,853 kWh
Total units generated and purchased (G) excluding exports in May, 2020 = 889,450,752 kWh
ROBERT PAVEL OIMEKE,
MR/0455081
Director-General.
Extracted Entities (1)
previous_gazette_ref
3949
Details
- Signed By
- ROBERT PAVEL OIMEKE
- Title
- Director-General
- Date Signed
- 12th June 2020
- Page
- 13
- Extraction Method
- regex
Source Gazette
Vol. CXXII No. 109
Published 27th February 2020