Back
REGULATION
100% confidence
via regex
GAZETTE NOTICE NO. 5411
GAZETTE NOTICE NO. 5411
THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
(No. 8 of 1999)
REGULATION
PURSUANT to regulation 21 of the Environmental Management
and Co-ordination (Impact Assessment and Audit) Regulations, 2003,
the National Environment Management Authority (NEMA) has
received an Environmental Impact Assessment Study Report for the
above proposed project.
The proponent, Murang'a South Water and Sanitation Company
(MUSWASCO), is proposing to construct a sewerage infrastructure
for Sabasaba, Maragua and their surrounding areas to be financed by
World Bank and implemented through Water Sector Trust Fund
(WSTF). This initiative is under the umbrella of Up scaling Basic
Sanitation for the Urban Poor (UBSUP) and involves construction of
DTF of capacity 50 m3/day in Sabasaba Town, Murang'a County. The
DTF will be used to treat the waste water from residential dwellings
and institutions in Sabasaba, Maragua Town and the environs. Septage
will be collected from latrines and septic tanks by exhausters,
transported to the DTF, treated and effluent discharged to Sabasaba
River after treatment to meet the WHO standard while sludge will be
used as fertilizer.
The following are the anticipated impacts and proposed mitigation
measures:
Environmental/S
ocial Impact Proposed Mitigation Measures
Environmental
degradation
risks
• Construction activities will be limited to
Project sites/routes which already exist
therefore limited destruction to vegetation
cover.
• Stock piling of top soil, construction material
and wastes should be done only at designated
sites approved by the supervising engineer,
erosion prevention through berming of loose
soil sites should be done in all areas
susceptible to agents of erosion.
• Utilize to the extent possible the existing
public roads to avoid social and economic
disruption.
• Ensure road safety measures for the
construction vehicles to the extent possible by
observing all traffic regulations.
• The contractor will be required to provide for
the appropriate environmental training and
awareness in his costs and programming.
• The contractor and sub-contractors shall be
aware of the environmental requirements and
constraints on construction activities contained
in the provisions of this ESMP.
• An initial environmental awareness training
session shall be held prior to any work
commencing on site, with the target audience
being all project staff.
Risks of
increased social
ills such as drug
use, HIV and
Aids
transmission in
the area
• The contractor shall institute HIV/AIDS
awareness and prevention campaign amongst
his workers for the duration of the contract,
contracting and implementing organization,
with preference for an organization already
working on this issue in the Project area.
• Prohibit drug abuse within the project site.
Social conflicts
and security
• Accommodate the views raised during
stakeholder meetings.
• Post emergency and SOS numbers strategically
throughout the project lifecycle.
• Incorporate lighting during designs within the
site to enhance security.
Environmental/S
ocial Impact Proposed Mitigation Measures
• Liaise with the administration units such as the
police and local administration to provide
regular surveillance and patrols to protect
workers and the neighbourhood.
Public/
community
health and
safety risks
• Notify public the intent to cut sections of the
road for safety precautions.
• Provide signage and safety information in all
work areas.
• Ensure that no poorly constructed temporary
structures, roads or bridges that may collapse
and kill/injure members of community or
damage neighboring properties.
• The contractor will do proper fencing or
boundary controls to prevent site access from
unauthorized personnel and members of the
community (especially children).
• The contractor will Isolate the site for access
by the local communities during the
construction for their safety and health.
• Contractor to provide a Healthy and Safety
Plan prior to the commencement of works to
be approved by the resident engineer.
Disruption of
amenities
(access roads,
services lines
and driveways)
causing
inconveniences
to the
community
• Notify other services providers.
• Open small sections that can be reinstated
within the shortest period to avoid public
disruption.
• Mark the lines to avoid conflicts with other
activities.
Risks of
contaminating
surface and
ground water
resources
• Construction wastes (residual earth, debris and
scrap materials) to be removed for safe
disposal.
• Encourage reuse where possible (concrete
debris for access road surfacing).
• Contaminated organic matter in the work areas
to be isolated for safe disposal.
• Material residuals to be disposed off in
accordance with established regulations.
Risks of solid
waste
mismanageme-
nt leading to
pollution
• Provide sludge drying beds in the project.
• Provision of adequately designed bins to
prevent access by vermin.
• Monitor skips so that they do not become
overfilled.
• Ensure that the solid waste collected is
disposed of in an approved dumpsite.
Risks of
accidents,
injuries or death
of workers
• Conduct job-specific risk assessments/job
safety analysis/ safe work procedures.
• Conduct statutory health and safety and first
aid trainings.
• Ensure that there is OHS committee
representative/ OHS reporting line for effective
OHS supervision.
• Provide construction workers with personal
protective gear (gloves, gum boots, overalls
and helmets),
• Provide temporary toilets and bathrooms for
the construction workers at the work sites.
• Provide onsite first aid kit accessible by the
workers on need.
30th July, 2020 THE KENYA GAZETTE
Environmental/S
ocial Impact Proposed Mitigation Measures
Hazards of fire
outbreak, oil
and chemical
spills.
• Follow specifications of the Occupational
Health and Safety Act, EMCA1999 and
others in the development and operation of
stores.
Air pollution
causing
respiratory
disorders to
human
• Monitor and ensure that influent sulphate
levels are below 240 mg/l.
• Ensure that the pond series have adequate
water flow to reduce the potential of odour
formation. Vehicles delivering soil materials
shall be covered to reduce spills and
windblown dust.
• Water sprays shall be used on all earthworks
areas within 200metres of human settlement.
Noise and
vibration
control from
plant and
equipment
• The contractor shall keep noise level within
acceptable limits and construction activities
shall, where possible, be confined to normal
working hours in the residential areas.
• The contractor must adhere to Noise
Prevention and Control Rules of April 2005.
Increase in traffic
along the access
road
• Limit septage delivery to the site between the
hours of 8 and 5 p.m. This will limit the noise
nuisance to residents and possibly reduce the
population exposed to potential accidents, as
most persons would have already left their
homes to go to work or and schools.
• Add adequate personnel and appropriate signs
including speed limits along the road in
proximity to the access roads to control
movement of workers, equipment and goods to
and within construction site.
Poor depositing
of septage by
cess pool
emptier
• Institute and maintain a ticketing system for
cesspool emptiers, where upon successful
disposal, the WWTP operator would issue a
receipt to the cesspool emptier.
• County Government and NEMA should put in
place a system to monitor cesspool service
providers and in addition, have a public
educational campaign to educate and inform
the public about the system.
Accidents
occurrence and
sicknesses
• Install safety valves on gas conveyance
system.
• Make prior arrangements with healthcare
facilities such as a Health Centre in proximity.
• Design and implement an emergency response
plan.
Pollution of local
stream
• Follow the NEMA waste water quality
guidelines strictly.
• Keep the sewer treatment plant clean to limit
the attraction of birds which scavenge for
insects and maggots from the ponds and sludge
beds.
• The sewage treatment plants should be
protected from wildlife encroachments by
providing secure barriers to keep off the
animals from interfering with the plant
operations and safety. This will also ensure
safety of the residents.
• Storm water discharge leading to erosion and
downstream flooding should be controlled and
monitored.
The full report of the proposed project is available for inspection
during working hours at:
(a) Principal Secretary, Ministry of Environment and Forestry,
NHIF Building, Community, P.O. Box 30126–00100,
Nairobi.
(b) Director-General, NEMA, Popo Road, off Mombasa Road,
P.O. Box 67839–00200, Nairobi.
(c) County Director of Environment, Murang’a County.
A copy of the report can be downloaded at www.nema.go.ke
The National Environment Management Authority invites
members of the public to submit oral or written comments within
thirty (30) days from the date of publication of this notice to the
Director-General, NEMA, to assist the Authority in the decision
making process regarding this plan.
Comments can also be emailed to dgnema@nema.go.ke
MAMO B. MAMO,
Ag. Director-General,
MR/0783613 National Environment Management Authority.
Dated the 30th July, 2020.
MAMO B. MAMO,
Ag. Director-General, National Environment Management Authority.
Extracted Entities (1)
previous_gazette_ref
5411
Details
- Act / Legislation
- THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
- Reference
- No. 8 of 1999
- Signed By
- MAMO B. MAMO
- Title
- Ag. Director-General, National Environment Management Authority
- Date Signed
- 30th July 2020
- Page
- 21
- Extraction Method
- regex
Source Gazette
Vol. CXXII No. 147
Published 10th January 2020