GAZETTE NOTICE NO. 101
PURSUANT to clause 5 of Part III of the Schedule of Tariffs 2018, notice is given that all prices for electrical energy specified in Part II -
(A) of the said Schedule will be liable to a Water Resource Management Authority (WRMA) levy of plus 2.22 Kenya cents per kWh for all meter
readings to be taken in January, 2020.
Information used to calculate the WRMA levy:
Approved WRMA levy for energy purchased from hydropower plants of capacity equal to or above 1MW = 5 Kenya cents per KWh.
Units Purchased in October, 2019
Hydropower Plant (Kwh.)
Gitaru 90,107,000
Kamburu 37,001,000
Kiambere 98,310,000
Kindaruma 21,532,460
Masinga 1,582,000
Tana 13,057,315
Wanjii -
Sagana 1,031,697
Ndula -
Turkwel 34,761,860
Gogo 395,068
Sondu Miriu 43,870,000
Sangoro 13,992,480
Regen-Terem 3,253,737
Chania 107,594
Gura 1,265,850
Total units purchased from hydropower plants with capacity equal to or above 1MW = 360,268,061 kWh
Total units generated and purchased (G) excluding exports in October, 2019 = 951,704,631 kWh
ROBERT PAVEL OIMEKE,
MR/0455081 Director-General.
Extracted Entities (1)
previous_gazette_ref
101
Details
- Signed By
- ROBERT PAVEL OIMEKE
- Title
- Director-General
- Page
- 9
- Extraction Method
- regex
Source Gazette
Vol. CXXII No. 4
Published 3rd January 2020