Back
AUTHORIZATION
100% confidence
via regex
GAZETTE NOTICE NO. 42
GAZETTE NOTICE NO. 42
THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
(No. 8 of 1999)
AUTHORIZATION
Pursuant to Regulation 21 of the Environmental Management and
Co-ordination (Impact Assessment and Audit) Regulations, 2003, the
National Environment Management Authority (NEMA) has received
an Environmental Impact Assessment Study Report for the above
proposed project
The proponent, Rift Valley Water Works Development Agency, is
proposing to set up the Malaba Sewerage Project in Busia County. The
project consists of two main areas-setting up a new sewerage pipeline
system and setting up a sewerage treatment plant. The proposed
sewerage works will consist of; preliminary treatment consisting of
inlet chamber, screening, grit chambers and measuring parshall flume,
sewers of sizes ranging from 100mm total lengh 9.2 Km and
consisting of 9 sewer lines, three main trunk sewer lines of diameter
200-600mm UPVC and concrete pipes and total length about 16km, a
total of 12 waste stabilization ponds are proposed to be constructed to
treat totsl of up to 4000m3/day of waste water. The ponds consist of
3No. anaerobic, 3No. facultative and 6No. maturation ponds, total area
for the ponds is approximately 450m by 300m including space for
future expansion.
The following are the anticipated impacts and proposed mitigation
measures:
Impacts Proposed Mitigation Measures
Air quality
control
• Workers shall be trained on management of air
pollution from vehicles and machinery.
• All construction machinery shall be maintained
and serviced in accordance with the contractor’s
specifications.
• The removal of vegetation shall be avoided until
such time as clearance is required.
• Exposed surfaces shall be re-vegetated or
stabilized as soon as practically possible.
• The contractor shall not carry out dust
generating activities (excavation, handling and
transport of soils) during times of strong winds.
• Vehicles delivering soil materials shall be
covered to reduce spills and windblown dust.
• Water sprays shall be used on all earthwork’s
areas within 200 metres of human settlement.
Associated risks
of
environmental
degradation
• The site is to be cleared of all construction
materials, including litter prior to hand over.
• Fences, barriers and demarcations associated
with the construction phase must be removed
from the site.
• Rehabilitation Activities of Environmental
Cases identified must continue throughout the
defect liability period.
Risk of sewer
blockage and
overflows to the
environment
(polluting River
Malaba
• Awareness raising among community members
not to dump solids in manholes.
• Development of an inventory of system
components, with information including age,
construction materials, and drainage areas
served elevations.
• Design manhole covers to withstand anticipated
loads and ensure that the covers can be readily
replaced if broken.
• Ensure sufficient hydraulic capacity to
accommodate peak flows and adequate slope in
gravity mains to prevent build-up of solids and
hydrogen sulphide generation.
Risk of illegal
connection to
the sewer
pipeline
• Constant inspection by BUWASCO officials to
identify and repair leakages.
• Conduct public sensitization programs on
importance not interfering with the water
pipeline and the need to seek official water
connection from BUWASCO.
Risk of
encroachment
and construction
of structures on
the sewer way
leaves
• Mapping and installation of beacons to which
illustrate the width of the pipeline reserve.
• Regular inspection of the pipeline corridor for
encroachment.
• Prosecution of encroachers as required by Busia
County By-laws on way leaves and road
reserves maintenance.
THE KENYA GAZETTE 3rd January, 2020
24 24
Impacts Proposed Mitigation Measures
• Conduct public sensitization programs on
importance not interfering with way leaves and
public reserve land.
Soil
Contamination
• The BUWASCO to attend to burst pipes
promptly to prevent excessive loss of soil.
• Provide high risk areas with appropriate
drainage for effective channeling of burst
sewage spills.
• Encourage land owners along sewer lines to
maintain vegetated belts along the pipeline to
control any overflows flows and trap soil.
• Mark clearly the pipeline for ease of
identification and protection by the adjacent
landowners.
Solid waste
accumulation
• Use of an integrated solid waste management
system through a hierarchy of options.
• All buildings, machinery, equipment, structures
and partitions that will not be used up must be
removed and recycled/reused.
• All foundations must be removed and recycled,
reused or disposed of at a licensed disposal site.
• Where recycling/reuse of the machinery,
equipment, implements, structures, partitions
and other demolition waste is not possible, the
materials should be taken to a licensed waste
disposal site.
• Donate reusable demolition waste to charitable
organizations, individuals and institutions.
Change in
landscape (both
built and natural
• Implement an appropriate revegetation
programme.
• Rehabilitate the affected locations to the
satisfaction of NEMA and other.
• Consider use of indigenous plant species in re-
vegetation.
• Trees should be planted at suitable locations so
as to interrupt slight lines (screen planting)
between the adjacent area and the development.
Environmental
and safety risks
associated with
burrowing and
opening up of
new quarry sites
• Ensuring that appropriate authorization to use
the proposed borrows pits and quarries have
been obtained before commencing activities.
• Topsoil shall be stripped prior to removal of
borrow and stockpiled onsite. This soil shall be
replaced on the disturbed once the operation of
the borrow site or quarry is complete.
• Construction material sources should be
environmentally sustainable (approved
accordingly).
• Delivery routes and modes of transport should
be approved.
• Material storage on site not to be internal or
external nuisance.
Risks of
contaminating
surface and
underground
water resources
• Construction wastes (residual earth, debris and
scrap materials) to be removed for safe disposal.
• Contaminated organic matter in the work areas
to be isolated for safe disposal.
• Material residuals to be disposed of in
accordance with established regulations.
Occupational
health and
safety
• Provide construction workers with personal
protective gear (gloves, gum boots, overalls and
helmets).
• Provide onsite first aid kit accessible by the
workers on need.
Impacts Proposed Mitigation Measures
• Isolate the site for access by the local
communities during the construction for their
safety and health.
• Contractor to provide a Healthy and Safety Plan
prior to the commencement of works to be
approved by the resident engineer.
Traffic
management on
site
• Strict use of warning signage and tapes where
the trenches are open and active sites.
• Employ and train road safety Marshalls who will
be responsible for management of traffic on site.
• Contractor to provide a traffic management plan
during construction to be approved by the
resident engineer.
The full report for the proposed project is available for inspection
during working hours at:
(a) Principal Secretary, Ministry of Environment and Forestry,
NHIF Building, P.O. Box 30126–00100, Nairobi.
(b) Director-General, NEMA, Popo Road, off Mombasa Road,
P.O. Box 67839–00200, Nairobi.
(c) County Director of Environment, Busia County.
The National Environment Management Authority invites
members of the public to submit oral or written comments within
thirty (30) days from the date of publication of this notice to the
Director-General, NEMA, to assist the Authority in the decision
making process for this project.
MAMO B. MAMO,
Ag. Director-General,
MR/0440842 National Environment Management Authority.
Dated the 3rd January, 2020.
MAMO B. MAMO,
Ag. Director-General, National Environment Management Authority.
Extracted Entities (1)
previous_gazette_ref
42
Details
- Act / Legislation
- THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
- Reference
- No. 8 of 1999
- Signed By
- MAMO B. MAMO
- Title
- Ag. Director-General, National Environment Management Authority
- Date Signed
- 3rd January 2020
- Page
- 23
- Extraction Method
- regex
Source Gazette
Vol. CXXII No. 1
Published 3rd January 2020