GAZETTE NOTICE NO. 8144
GAZETTE NOTICE NO. 8144
THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
(No. 8 of 1999)
ACT
PURSUANT to section 59 of the Environmental Management and
Co-ordination Act, 1999, the National Environment Management
Authority (NEMA) has received an Environmental Impact Assessment
Study Report for the above proposed project.
The proponent, Festus Mwaniki Lonzi, proposes to develop a
10No storey(Ground floor parking spaces, 180 No. one bedroom and
40No. bedsitters units) totaling to 220 residential units, overhead and
underground water storage facility, power and a stand-by generator,
associated facilities and amenities in Embakasi East, Nairobi City
County.
The following are the anticipated impacts and proposed mitigation
measures
Possible Impacts Mitigation Measures
Soil erosion • Control earthworks; install drainage
structures properly, ensure management
of excavations activities.
Air pollution • Stockpiles of earth should be sprayed
with water or covered during the dry
seasons.
• Provide dust masks for the personnel in
dust generation areas; Sensitize
construction workers on pollutions
control measures.
Noise pollution • Sensitize workforce including drivers of
construction vehicles; Install sound
barriers for pile driving activity.
• Install portable barriers to shield
compressors and other small stationary
equipment where necessary.
• Display signs to indicate construction
activities.
• Maintain all equipment, Workers in the
vicinity of high level noise to wear
safety protective gear.
Exhaust emissions • Vehicles idling time to be minimized;
Equipment shall be properly serviced
and maintained.
Increased water use • Installation of motion sensing taps to
automatically switch off ;Rainwater
harvesting to be done; Avail storage
tanks.
Waste management • Garbage shall be disposed periodically;
Contract a NEMA licensed waste
handler.
Public health and occupational
safety
• Ensure proper solid waste disposal and
collection facilities.
• Ensure dustbin cubicles are protected
from animals.
• Provide safety gears for all personnel.
• Proper treatment of waste waters.
Emission of greenhouse
gas
• Installation of Solar PV system to
supplement KPL supply.
• Implantation of energy efficiency
mechanism to reduce energy
consumption.
• Undertaking annual energy audits to
monitor progress for efficiency.
Climate change risksand
vulnerability
• Water management.
• Invest in water management strategies
like rainwater harvesting.
• Efficient water use practices to mitigate
water scarcity during dry periods and
reduce floods risks during heavy rainfall
events.
• Infrastructure Designs.
• Incorporate resilient features to
withstand extreme weather like flooding
storms and high temperatures.
• Energy Efficiency.
• Implement technologies and practice to
reduce greenhouse gas emissions and
dependency on fossils fuels.
20th June, 2025 THE KENYA GAZETTE
Possible Impacts Mitigation Measures
Traffic disruption • Plan transportation of materials so as to
reduce on the number of trips or the
number of vehicles on the access roads.
• Employment of flagmen to ensure
public safety.
• Signage’s to alert drivers to be cautious.
Fire risks • Install fire alarm with smoke sensors.
• Have standby fire extinguishers at the
site.
• Declare places with flammable
materials as “NO SMOKING ZONES”
and display Conspicuous notices of the
same.
The full report of the proposed project is available for inspection
during working hours at:
(a) Principal Secretary, Ministry of Environment, Climate
Change and Foresty, NHIF Building, 12th Floor, Ragati
Road, Upper Hill, Upper Hill, P.O. Box 30126–00200,
Nairobi.
(b) Director-General, NEMA, Popo Road, off Mombasa Road,
P.O. Box 67839–00200, Nairobi.
(c) County Director of Environment, Nairobi City County.
A copy of the EIA report can be downloaded at www.nema.go.ke
The National Environmental Management Authority, invites
members of the public to submit oral or written comments within
thirty (30) days from the date of publication of this notice to the
Director-General, NEMA to assist the Authority in the decision
making process for this project.
Comments can also be e-mailed to dgnema@nema.go.ke
MAMO B. MAMO,
MR/4545918 Director-General,
Dated the 20th June, 2025.
MAMO B. MAMO,
Director-General,.
Extracted Entities (1)
previous_gazette_ref
8144
Details
- Act / Legislation
- THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
- Reference
- No. 8 of 1999
- Section
- section 59
- Signed By
- MAMO B. MAMO
- Title
- Director-General,
- Date Signed
- 20th June 2025
- Page
- 50
- Extraction Method
- regex
Source Gazette
Vol. CXXVII No. 132
Published 5th February 2025