GAZETTE NOTICE NO. 7326
GAZETTE NOTICE NO. 7326
THE ENERGY ACT
(Cap. 314)
ACT
NOTICE is given pursuant to section 11 (b) of the Energy Act No. 1 of 2019 that the Energy and Petroleum Regulatory Authority has reviewed and approved the applicable Kenya Pipeline Company’s (KPC) multi-year pipeline transport tariff for the tariff control period 2025/2026–2027/2028 as follows:
Financial Year Applicable tariff (KSh/ m3/km)
2025-2026 5.44
2026-2027 5.53
2027-2028 5.83
The breakdown for local and export tariff is as follows:
2024/25 Approved Tariff
Applicable Depot Tariffs
2025/26 2026/27 2027/28
Pipeline Tariff KSh./m3/km 5.44 5.44 5.53 5.83
Moi Airport (USD/m3) 25.29 21.99 22.17 23.45
JKIA (USD/m3) 25.29 21.99 22.17 23.45
Nairobi Terminal (KSh./m3) 2,791.85 2,851.80 2,874.13 3,040.60
Nakuru Terminal Local KSh./m3 3,467.62 3,529.08 3,562.06 3,751.17
Export USD/m3 31.42 27.22 27.47 28.93
Eldoret Terminal Local KSh./m3 4,175.37 4,238.42 4,282.55 4,495.37
Export USD/m3 37.83 32.69 33.03 34.67
Kisumu Terminal Local KSh./m3 4,171.37 4,234.41 4,278.48 4,491.16
Export USD/m3 37.79 32.66 33.00 34.64
Konza (Kshs./m3) Local KSh./m3 1,527.48 1,530.89 1,554.96 1,606.13
Export USD/m3 11.81 11.99 12.39
The effective date of the above set of tariffs is 15th April 2026 and subsequent adjustments for the next tariff control period will be on 15th July of every year.
JOSEPH OKETCH, MR/8126752 Ag. Director-General.
Dated the 15th April, 2026.
JOSEPH OKETCH,
Ag. Director-General.
Extracted Entities (1)
previous_gazette_ref
7326
Details
- Act / Legislation
- THE ENERGY ACT
- Reference
- Cap. 314
- Section
- section 11 (b)
- Signed By
- JOSEPH OKETCH
- Title
- Ag. Director-General
- Date Signed
- 15th April 2026
- Page
- 43
- Extraction Method
- regex
Source Gazette
Vol. CXXVIII No. 83 (SUPPLEMENT)
Published 15th May 2026