GAZETTE NOTICE NO. 9793
GAZETTE NOTICE NO. 9793
THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
(Cap. 387)
RESTORATION
PURSUANT to section 59 of the Environmental Management and
Co-ordination Act, Cap. 387, the National Environment Management
Authority (NEMA) has received an Environmental Impact Assessment
Study Report for the above proposed project.
The proponent, County Pension Fund, proposes to construct a 43 storey office block comprising of parking silos, conference rooms, podium, offices, restaurant, roof terrace, observation deck, associated facilities and amenities on plot L.R. Nos. 13/793,794,795,796 and 801, along Masaba Road, Upperhill, Nairobi City County.
The following are the anticipated impacts and proposed mitigation measures:
Impacts Mitigation measures
Soil erosion • Control earthworks; Install drainage structures properly;
3186 3186
Impacts Mitigation measures
• Ensure management of excavation activities, • Control activities especially during rainy conditions, • Provide soil erosion control and conservation structures.
Loss of
Vegetation
• Only the area marked for development will be cleared;
• Restore/re-establish vegetation in some parts of the disturbed areas through implementation of landscaping program.
Air Pollution • All trucks and any other mode of hauling soil sand and other loose materials to and from site should be covered.
• Sprinkling water on dry soils in excavated areas, pavements.
• Use of clean fuels for machines and equipment.
• Stockpiles of earth should be sprayed with water or covered during dry seasons;
• Provide dust masks for the personnel in dust generation areas; Sensitize construction workers on pollution control measures
Emission of
Green House
Gases
• Installation of a solar PV system on the rooftop to supplement KPC supply thereby abating about GHG emissions.
• Implementing energy efficiency mechanisms to reduce energy consumption.
• Undertaking annual energy audits to monitor progress and exploit opportunities for energy efficiency
Fire risks • Install fire alarm with smoke sensors;
• Have standby fire extinguishers at the site in case fire erupts;
• Declare places with flammable construction materials as ‘’NO SMOKING ZONES’’ and display conspicuous notices of the same.
Traffic
Disruption
• Properly plan for transportation of materials to ensure that vehicles are optimally filled to reduce the number of trips done or the number of vehicles on the access roads;
• Employment of formal flagmen/women to ensure the public safety;
• Place clear signage’s at the gate to alert drivers to be cautious about the construction and to look out for entering and/or exiting vehicles;
• No overloading of trucks and practising good driving practices;
• Suitable junction/access point will be provided;
• The proponent shall undertake a traffic Impact
Assessment and generate traffic management plan which will be implemented throughout the project cycle.
Noise pollution • Sensitize workforce including drivers of construction vehicles;
• Install sound barriers for pile driving activity;
• Install portable barriers to shield compressors and other small stationary equipment where necessary;
Impacts Mitigation measures
• Display signs to indicate construction activities;
• Maintain all equipment;
• Workers in the vicinity of high-level noise to wear safety and protective gear.
Occupational
Safety and
Health
• All workers and workers and visitors on site to use mandatory protective gear.
• Unattended entry to the project site to be restricted.
• Use of efficient and well-maintained machines to lift and transfer materials.
• Removal of all dangerous materials that may pose a threat such as metal bars, wires, glass and broken equipment.
• Availing of fully equipped first aid kits to help address emergencies. Warning signs to all users and visitors be placed at appropriate places.
• Educate construction works and tenants on health and safety risks and their prevention.
Public health, occupational health and safety
• Train staff/ workers on occupational health and safety.
• Provide full protective gear& workmen’s compensation cover in addition to the right tools and operational instructions.
• Design of sewerage system should be as provided in the plans and should be constructed to approved size and design, standard and of approved materials.
• Avoid undesirable, substandard hazardous or unauthorized materials during construction and maintenance.
Contribution to
Climate
Change
• Water management;
• The project should invest in water management strategies like rainwater harvesting, storage facilities, and efficient water use practices.
• These measures aim to mitigate water scarcity during dry periods and reduce flood risks during heavy rainfall events.
• Infrastructure Design.
• Incorporate resilient features to withstand extreme weather like flooding, storms, and high temperatures.
• Energy Efficiency:
• Implement technologies and practices to
• Reduce greenhouse gas emissions and dependency on fossil fuels. Biodiversity
Conservation:
• Protect and enhance natural ecosystems to preserve biodiversity and ecosystem services, including reforestation, habitat restoration, and sustainable land management practices
Insecurity and social impacts
• Provision of security guards, CCTV cameras, security lights and other security apparatus during the entire project cycle.
• Adhere to work timings in line with the NEMA licensing conditions.
26th June, 2026 THE KENYA GAZETTE
Impacts Mitigation measures
Increased Water
Use
• Installation of motion-sensing taps, urinals, and toilets to automatically switch off once the user leaves the station.
• A motion sensor tap would cut up to 85% of annual water usage compared to conventional taps. Rainwater harvesting:
• The harvested water would be used for cleaning, flushing toilets, watering plants, etc. Avail storage tanks.
Increased
Generation of
Waste
• Adoption of waste minimization at the source, adhering to Waste management regulation, 2025, build construction workers’ capacity on sanitation and hygiene practises.
• Segregation of waste at the source during the project cycle.
• Special attention shall be paid to the sanitary facilities on site.
• Garbage shall be disposed periodically.
• Contract a NEMA licensed waste handler.
Sewerage infrastructure
• The design for the entire sewerage system shall consider the estimate discharges from individual sources and the cumulative discharge of the entire project even during peak volumes;.
• provide for adequate drainage systems, ensure effluents are discharged responsibly to the sewerage system;
• The developer will seek approval from NWSC before re-connecting to the existing sewer system;
• Monitoring of the wastewater to ensure compliance with the Environmental
Management & Coordination (Water Quality)
Regulations, 2025 and other relevant laws.
Power Sources • Power supply requirements shall be calculated and shared with KPLC as is the requirement.
• A dedicated transformer for the entire project shall be a consideration.
• Alternative power sources (solar) shall be installed for lighting and heating.
The full report of the proposed project is available for inspection during working hours at:
(a) Director-General, NEMA, Popo Road, off Mombasa Road, P.O. Box 67839–00200, Nairobi.
(b) County Director of Environment, Nairobi City County.
A copy of the report can be downloaded at www.nema.go.ke
The National Environment Management Authority invites members of the public to submit oral or written comments within thirty (30) days from the date of this publication to the Director-
General, NEMA, to assist the Authority in the decision making process regarding this project. Kindly quote Ref. No.
NEMA/ENVIS/SR/00581.
Comments can also be e-mailed to info@nema.go.ke
MAMO B. MAMO, Director-General, MR/7807212 National Environment Management Authority.
Dated the 26th June, 2026.
MAMO B. MAMO,
Director-General, National Environment Management Authority.
Extracted Entities (1)
previous_gazette_ref
9793
Details
- Act / Legislation
- THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
- Reference
- Cap. 387
- Section
- section 59
- Signed By
- MAMO B. MAMO
- Title
- Director-General, National Environment Management Authority
- Date Signed
- 26th June 2026
- Page
- 37
- Extraction Method
- regex
Source Gazette
Vol. CXXVIII No. 110 (SUPPLEMENT)
Published 26th June 2026