GAZETTE NOTICE NO. 42
GAZETTE NOTICE NO. 42
THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
(No. 8 of 1999)
REGULATION
PURSUANT to regulation 21 of the Environmental (Impact
Assessment and Audit) Regulations, the National Environment
Management Authority (NEMA) has received an environmental impact assessment study report for the rehabilitation and augmentation of existing Garissa Sewerage System, Garissa District.
The proposed project entails rehabilitation and augmentation of existing Garissa Sewerage System, Garissa District.
The project anticipates the following impacts and mitigation measures.
Possible impacts Mitigation measures
1.Rise in ground water table • Enhance proper workmanship during construction.
2.Disease hazards problem • Refill borrow area to avoid ponding
3.Operation and
• Garissa Water and Sanitation maintenance of the new
Company (GAWASCO) to recruit sewerage system.
more staff to man the sewage.
•Train staff in sewerage maintenance works and attitude change.
•Purchase adequate maintenance equipment, vehicles and motor- cycles
4.Occupational health safety • Provide protective gear to the sewerage maintenance staff.
5.Solid waster management • Increase collection efficiency.
6.Impact on project land • Sensitization of the community
Possible impacts Mitigation measures
7.Impact on wildlife • Enforce wildlife passage corridor as per Bouragi draft physical development plan.
The full report of the proposed project is available for inspection during working hours at:
(a)The Director-General, National Environment Management
Authority, Kapiti Road, off Mombasa Road, P.O. Box
67839-00200, Nairobi.
(b)The Permanent Secretary, Ministry of Environment and
Natural Resources, National Hospital Insurance Fund
Building, Community, 4th Floor, P.O. Box 30521, Nairobi. •
(c)Provincial Director of Environment, North Eastern Province.
(d)District Environment Officer, Garissa District.
The National Enyironment Management Authority invites members of the public to submit oral or written comments within thirty (30) days from the date' of publication of this notice to the
Director-General, National Environment Management Authority, to assist the authority in the approval process of the project.
Dated the 7th May, 2008.
A. M. KARIUKI, for Director-General, National Environment Management Authority.
Gazon NOTICE No. 4454
THE ENVIRONMENTAL MANAGEMENT AND
CO-ORDINATION ACT
(No. 8 41999)
THE NATIONAL ENVIRONMENT MANAGEMENT
AUTHORITY
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT
FOR THE PROPOSED ADDITIONAL PETROLEUM TANKS AND
A TRUCK OFF-LOADING FACILITY AT THE NATIONAL
NAIROBI TERMINAL DEPOT
INVITATION OF PUBLIC COMMENTS
PURSUANT to regulation 21 of Environment (Impact Assessment and Audit) Regulations, the National Environment Management
Authority (NEMA) has received an environmental impact assessment study report for the implementation of proposed additional petroleum tanks and a truck off-loading facility at the National Nairobi Terminal depot.
The main objective of the project is to enhance the security of petroleum products supply to the proponent's customer in Kenya, East
Africa and the great lakes region.
The project is located at the National Nairobi Terminal Depot, within National Oil Corporation of Kenya compound.
The Project anticipates the following impacts and mitigation measures.
Possible impact
Mitigation measures
1. Waste management
• Atmospheric emissions should comply with international air quality regulations.
•Ensure Nairobi City. Council standards for sewage management.
•Waste to be sorted and disposed according to Legal Notice No. 121 of
2006; Waste Regulations and Nairobi
City Council requirements.
•Metal to be salvaged.
•Potentially contaminated hydrocarbon wastewater will be discharged in compliance with Legal Notice No. 120
Possible impact
Mitigation measures of 2006; Water Quality Regulations.
•Process areas will be paved and curbed to avoid contaminating storm water.
2. Air emissions
• Use of dust suppressions techniques.
•Air emissions from the construction equipment • will be localized and temporary.
•Routine inspection and maintenance of construction equipment.
3. Waste water discharge • Process areas will be curbed to contain any spills and runoff.
•Develop a storm management plan.
•Potentially contaminated waste water will be treated in an oil water separator that will be monitored regularly for effluent quality.
•Use of reinforced concrete foundations for the tanks, use of impermeable membranes.
4. Noise pollution
• Ensure that noise generated does not exceed the Kenya national guidelines at the property boundaries.
The full report of the proposed project is available for inspection during working hours at:
(a)Director-General, NEMA, Kapiti Road, off Mombasa Road
P.O. Box 67839-00200, Nairobi.
(b)Permanent Secretary. Ministry of Environment and Natural
Resources, N.H.I.F. Community, P.O. Box 30521, Nairobi.
(r) Provincial Director of Environment, Nyayo House.
(d) District Environment Office, Nairobi East District.
NEMA invites members of the public to submit oral or written comments within thirty (30) days from the date of publication of this notice to the Director General, NEMA, to assist the Authority in the approval process of the project
B. M. LANGWEN, for Director-General, National Environment Management Authority.
Dated the 7th May, 2008.
A. M. KARIUKI,
for Director-General, National Environment Management Authority.
Extracted Entities (1)
previous_gazette_ref
42
Details
- Act / Legislation
- THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
- Reference
- No. 8 of 1999
- Signed By
- A. M. KARIUKI
- Title
- for Director-General, National Environment Management Authority
- Ministry
- Ministry of Environment
- Date Signed
- 7th May 2008
- Page
- 45
- Extraction Method
- regex
Source Gazette
Vol. CX No. 40 (SUPPLEMENT)
Published 23rd May 2008