GAZETTE NOTICE NO. 3898
GAZETTE NOTICE NO. 3898
THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
(No. 8 of 1999)
REGULATION
PURSUANT to regulation 21 of Environmental (Impact
Assessment and Audit) Regulations, the National Environment
Management Authority, (NEMA) has received an environmental impact assessment study report for the implementation of the proposed
LPG ―common user‖ bulk storage and filling depot.
The proposed project entails installation of a modern medium size
―Common User‖ LPG storage and filling plant. The depot will be designed in a modular form with an initial storage capacity of 100 metric tonnes and a filling rate of 1000 cylinders per hour. The filling container will be equipped with three electronic filling machines to fill
6kg, 12kg, 25kg and 35kg cylinders. Two (2) machines will be used to fill the 6kg and 12kg cylinders and one (1) machine will be dedicated to the 25kg and 35kg cylinders. The LPG storage will be composed of one (1) LPG tank with a geometrical capacity of 50m³. LPG tank is design to store mixture of Butane/Propane (with maximum propane content of 30%) and is design under the AD2000 code
The project is located in Kisumu East District in Winam Division, at Nyamasaria in Kasule Sub-location in Kisumu, about five kilometers away from Kisumu‘s Central Business District (CBD). It is located on Plot No. Kisumu/Kasule/399 on a 0.39 ha plot.
The following are the anticipated impacts and proposed mitigation measures:
Possible Impact Mitigation measures
Erosion and sedimentation
Drainage alteration
Concrete floors and cabro paving in the whole compound.
Installation of traps for stored loose construction materials such as sand.
Channel drains flowing under the perimeter walls and into the roadside drainages and culverts.
Water pollution Water Sprinkler System.
Ensure effective drainage into the sewer system.
Regular maintenance checks on drainage system.
Dust Regular watering of access routes to reduce dust.
Provision of dust masks to workers.
Emissions Use of mufflers on heavy equipment and vehicles.
Reduction in use of machinery to necessary requirement only.
Regular check of gas leak detection system, pipeline seams, pneumatic cut off system and remote operating valves for automatic cut-off of the system to cub greenhouse gas emissions.
Noise Operation during daylight hours only.
Provision of ear muffs to site workers.
Construction of high perimeter wall around the site.
Possible Impact Mitigation measures
Devegetation Minimal excavation.
Revegetation of bare areas.
Planting indigenous trees.
Solid waste disposal Ensure appropriate waste baskets available in offices.
Outsource a NEMA registered waste disposal agent to collect and dispose of solid waste.
Scrap materials and debris
Use of an integrated solid waste management system.
Waste generated will be characterized in compliance with standard waste management procedures.
Disposal locations will be selected by the contractor and the KCC based on the properties of the particular waste generated.
Vegetation disturbed
Soil erosion and drainage problem
Plant grass on areas that are not to be used for pathways and driveways.
Monitoring and inspection of the area for indications of erosion will be conducted and appropriate measures taken to rehabilitate any occurrences.
Fencing and signs restricting access posted to minimize disturbance to newly vegetated areas.
Drains planned and constructed.
Drains kept clean of debris.
Non hazardous waste
Disposal locations selected by contractor.
Use of an integrated solid waste management system.
Hazardous wastes e.g.
spent solvents, oil spent, oil sludge, mercury contaminated and carbon beds
Waste treatment.
Waste generated will be characterized in compliance with standard waste procedures.
Fire and or explosion Install smoke detectors at strategic locations in the site.
Install gas detection system in a strategic location.
Install fire alarm systems.
Install hose reels system with a connection to a pressurized water supply along perimeter wall.
Place portable fire fighting canisters at conspicuous locations.
Institute speedy evacuation plans and fire drill training.
Install water tank with 500,000m³ of water.
Ensure impervious had standing areas with bunded sides draining away from tank area to hold accidental spillages.
Ensure supervision of deliveries.
Operating procedures instituted.
Install automatic shut-off devices.
Pollution of river
Nyamasaria and underground water bodies
Install Riflo Septica Sanitation System.
Install French drain to soak away the waste water.
The full report of the proposed project is available for inspection during working hours at:
(a) Director-General, the National Environment Management
Authority (NEMA), Popo Road, off Mombasa Road, P.O. Box
67839–00200, Nairobi.
(b) Permanent Secretary, Ministry of Environment and Mineral
Resources, N.H.I.F. Building, Community, P.O. Box 30521, Nairobi.
15th April, 2011 THE KENYA GAZETTE 1141
(c) Provincial Director of Environment, Nyanza Province.
(d) District Environment Officer, Kisumu East District.
The National Environment Management Authority invites members of the public to submit oral or written comments within thirty (30) days from the date of publication of this notice to the
Director-General, NEMA, to assist the Authority in the approval process of the project.
B. M. LANGWEN, for Director-General, MR1681706 National Environment Management Authority.
Dated the 15th April, 2011.
B. M. LANGWEN,
for Director-General, MR1681706 National Environment Management Authority.
Extracted Entities (1)
previous_gazette_ref
3898
Details
- Act / Legislation
- THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
- Reference
- No. 8 of 1999
- Signed By
- B. M. LANGWEN
- Title
- for Director-General, MR1681706 National Environment Management Authority
- Ministry
- Ministry of Environment And Mineral
- Date Signed
- 15th April 2011
- Page
- 75
- Extraction Method
- regex
Source Gazette
Vol. CXIII No. 35
Published 15th April 2011