GAZETTE NOTICE NO. 14082
GAZETTE NOTICE NO. 14082
THE ENVIRONMENTAL MANAGEMENT AND CO - ORDINATION ACT
(No. 8 of 1999)
REGULATION
Pursuant to regulation 21 of Environmental (Impact Assessment and Audit) regulations, the National Environmental Management
Authority (NEMA) has received an Environmental Impact Assessment
Study Report for the implementation of the proposed boundary wall, storey units, market stalls, bridges and footpaths.
The project involves the construction of boundary wall, 1490 residential and 1539 business relocation units, market stalls, bridges and footpaths.
THE KENYA GAZETTE 4th November, 2011
4288 4288
The project area stretches from the 534/6 km mark to the 539/9 km mark within the Nairobi- Kibera section (5.3 Km) and Likoni Road to
Mombasa Road within the Makadara- Embakasi section (7 Km) totaling some 12.3 Kilometers.
The following are the anticipated impacts and proposed mitigation measures:
Environment al/Social
Issue
Management & Mitigation and /or Enhancement
Measures
Oil spillage
Materials spillage
Littering the site
Ensure no spillage occurs
Ensure use serviceable machinery
Ensure no littering of the compound
Ensure safe storage of materials
Ensure accurate budgeting and estimation of actual construction material requirements to ensure that the least amount of material necessary is ordered.
Ensure that damage or loss of materials at the construction site is kept minimal through proper storage.
Use at least 5%-10% recycled refurbished or salvaged materials to reduce the use of raw materials and divert material from landfills.
Vegetation disturbance
Ensure proper demarcation and delineation of the project area to be affected by construction works.
Specify locations for vehicles and equipment, and areas of the site which should be kept free of traffic, equipment, and storage.
Designate access routes and parking within the site.
Introduction of vegetation (trees and grass) on open spaces and around the project site and their maintenance
Design and implement an appropriate landscaping programme to help in revegetation of part of the project area after construction.
Increased storm water, runoff and soil erosion
Surface runoff and roof water shall be harvested and stored in reservoirs so that it can be used for wetting and/or cooling purposes.
A storm water management plan that minimizes impervious area infiltration by use of recharge areas and use of detention and/or retention with graduated outlet control structure will be designed.
Apply soil erosion control measures such as levelling of the project site to reduce run-off velocity and increase infiltration of storm water into the soil.
Apply soil erosion control measures such as levelling of the project site to reduce run-off velocity and increase infiltration of storm water into the soil.
Ensure that construction vehicles are restricted to use existing graded roads
Ensure that any compacted areas are ripped to reduce run-off. Site excavation works to be planned such that a section is completed and rehabilitated before another section begins.
Interconnected open drains will be provided on site.
Roof catchments will be used to collect the storm water for some office uses.
Construction of water storage tanks to collect storm water for office and plant uses.
Increased solid waste generation
Use of an integrated solid waste management system i.e. through a hierarchy of options: 1.
Reduction at source 2. Recycling 3. Reusing
4.Incineration 5. Sanitary landfilling.
Through accurate estimation of the dimensions and quantities of materials required.
Use of durable, long-lasting materials that will not need to be replaced as often, thereby reducing the amount of construction waste generated over time
Provide facilities for proper handling and storage of construction materials to reduce the amount of waste caused by damage or exposure to the elements
Use building materials that have minimal or no packaging to avoid the generation of excessive packaging waste metal and plastic containers to reduce waste at site
Dispose waste more responsibly by contracting a registered waste handler who will dispose the wastes at designated sites or landfills only.
Waste collection bins to be provided at designated points on site
Air Pollution
Ensure strict enforcement of on-site speed limit regulations. Regularly watering access roads and borrow pit sites in close proximity to human settlements during the dry season in order to suppress dust generation and particulate settlement
Avoid excavation works in extremely dry weather.
Mixing should not be done on windy location
All access roads and work areas to be regularly sprinkled with water
Sprinkle water on graded access routes when necessary to reduce dust generation by construction vehicles
Personal Protective equipment to be provided to employees (breathing protection gear)
Noise and
Vibration
Sensitise construction vehicle drivers and machinery operators to switch off engines of vehicles or machinery not being used.
Sensitise construction drivers to avoid reversing of vehicle engines or hooting
Ensure that construction machinery is kept in good condition to reduce noise generation.
Limiting the extraction of gravel from borrow pits to normal working hours as legally provided for by Kenyan Laws and not outside
7:00 to 18:00 hours;
Ensure that all generators and heavy duty equipment are insulated or placed in enclosures (containers) to minimize ambient noise levels.
Trees to be planted around the site to provide some buffer against noise propagation
The noisy construction works will entirely be planned to be during day time when most of the neighbours will be at work
Increased energy consumption
Ensure electrical equipment, appliances and lights are switched off when not being used
Install energy saving bulbs/tubes at all lighting points instead of incandescent bulbs which consume higher electric energy
Plan well for transportation of materials to ensure that fossil fuels (diesel, petrol) are not consumed in excessive amounts
Monitor energy use during construction and set targets for reduction of energy use.
High Water
Demand
Water to be brought in from the City Water and Sewerage Company
Harness rainwater for office & gardening
Install water conserving taps that turn-off automatically when water is not being used
Promote recycling and reuse of water as much as possible
Install a discharge meter at water outlets to determine and monitor total water usage
Promptly detect and repair of water pipe and
4th November, 2011 THE KENYA GAZETTE tank leaks
Sensitise construction workers to conserve water by avoiding unnecessary toilet flushing etc
Ensure taps are not running when not in use
Generation of wastewater
Provide means for handling/treating sewage generated at the construction site
Provide means for handling/treating sewage generated at the construction site
Monitor effluent quality regularly to ensure that the stipulated discharge rules and standards are not violated
Ensure compliance with The OSHA (Building
Operations and Works of Engineering
Construction Rules), L.N. 40 of 1984
Human
Health And
Safety.
Sensitizing local communities not to allow children to play in flooded borrow pits during the rainy season; Conducting indoor spraying for mosquitoes. Conducting an awareness campaign covering construction equipment operators at borrow pits and the local community on matters of HIV/AIDS
Oil spills
Install oil trapping equipments in areas when there a likelihood of oil spillage such during the maintenance of construction equipment.
Soil in such an area will be well protected from contamination
Social and
Economic
Effects
Compensation and Relocation Plan to take into account compensation for loss of location shelter, trading stalls, crops and other structures. Limiting borrow pit sites to infertile and uncultivated pieces of land as much as is possible and Compensating individuals for any losses incurred to personal property as a result of the operation of the borrow pits.
Enhance consultations with the locals on the activities affecting them and include them on impact reduction
Solid waste generation
Provide solid waste handling facilities such as waste bins and skips
Ensure that solid waste generated at the proposed development is regularly disposed of appropriately at authorized dumping sites
Ensure that occupants of the proposed development manage their waste efficiently through recycling, reuse and proper disposal procedures.
Donate redundant but serviceable equipment to charities and institutions
Sewage release into environment
Provide adequate and safe means of handling sewage generated at the proposed
Energy
Consumption
Switch off electrical equipment, appliances and lights when not being used
Install energy saving fluorescent tubes at all lighting points within the proposed development instead of bulbs which consume higher electric energy
Monitor energy use during the operation of the project and set targets for efficient energy use
Sensitise the occupants to use energy efficiently
Water
Exploitation.
Promptly detect and repair of water pipe and tank leaks
Residents to conserve water e.g. by avoiding unnecessary toilet flushing.
Ensure taps are not running when not in use
Install water conserving taps that turn-off automatically when water is not being used
Install a discharge meter at water outlets to determine and monitor total water usage
Health & Implement all necessary measures to ensure
Safety Risks. health and safety of workers and the general public during operation of the proposed development project as stipulated in
Factories and Other Places of Work Act Cap
Safety &
Security of the premises and surrounding areas
Ensure the general safety and security at all times by providing day and night security guards and adequate lighting within and around the premises during night hours.
Hazard-warning signs ―NO SMOKING‖
The full report of the proposed project is available for inspection during working hours at:
(a) Director General, NEMA, Popo Road, off Mombasa Road, P.O.
Box 67839-00200, Nairobi.
(b) Permanent Secretary, Ministry of Environment and Mineral
Resources, NHIF Building, Community, P.O. Box 30521, Nairobi.
(c) Provincial Director of Environment, Nairobi Province.
(d) District Environment Officer, Westlands & Langata Districts.
(e) District Environment Officer, Embakasi & Makadara Districts.
The National Environment Management Authority invites members of the public to submit oral or written comments within sixty
(60) days from the date of publication of this notice to the Director
General, NEMA, to assist the Authority in the decision making process of the plan.
SALOME MACHUA, For: Director General, MR/8245563 National Environment Management Authority.
Dated the 4th November, 2011.
SALOME MACHUA,
For: Director General, National Environment Management Authority.
Extracted Entities (1)
previous_gazette_ref
14082
Details
- Act / Legislation
- THE ENVIRONMENTAL MANAGEMENT AND CO - ORDINATION ACT
- Reference
- No. 8 of 1999
- Signed By
- SALOME MACHUA
- Title
- For: Director General, National Environment Management Authority
- Ministry
- Ministry of Environment And Mineral
- Date Signed
- 4th November 2011
- Page
- 75
- Extraction Method
- regex
Source Gazette
Vol. CXIII No. 108
Published 4th November 2011