GAZETTE NOTICE NO. 13554
GAZETTE NOTICE NO. 13554
THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
(No. 8 of 1999)
ACT
PURSUANT to section 59 of the Environmental Management and
Co-ordination Act, 1999, the National Environment Management
Authority (NEMA) has received an Environmental Impact Assessment
Study Report for the above proposed project.
The proponent, Anno Investments Limited, proposes to construct a block of residential apartments comprising 3No. basement, ground floor and mezzanine (first) floors for parking space, and 2nd to 19th floors comprising a total of 177No. residential apartments (53No. two bedroom units, 123No. one bedroom units, 1No. Duplex Apartment unit) other associated facilities and amenities on Plot L.R. No. Nairobi
Block 19/610 (Original No. 1/579) along Kindaruma Road in
Kilimani, Nairobi City County.
The following are the anticipated impacts and proposed mitigation measures:-
Impacts Proposed Mitigation Measures
Soil erosion • Control earthworks.
• Install drainage structures to control flow of storm water.
• Ensure proper management of sustainable excavation activities.
Loss of vegetation • Only area earmarked for development should be cleared.
• Plant trees, shrubs and flowers on remaining open spaces.
Changes in hydrology/ impended drainage/deep excavations
• proper Installation of drainage structures.
• Install cascades to break the impact of water flowing in the drains.
THE KENYA GAZETTE 18th October, 2024
Impacts Proposed Mitigation Measures
• Ensure efficiency of drainage structures through proper design and maintenance.
• Provide gratings to the drainage channels.
• A geotechnical survey shall be conducted and the recommendations thereof followed. There shall be no blasting during excavation.
• A methodology for excavation shall be generated as required by NCA.
Air pollution • Stockpiles of earth should be sprayed with water or covered during dry seasons.
• Provide dust masks for personnel in dusty areas.
• Sensitize construction workers on pollution control measures.
• Cover all trucks hauling soil, sand and other loose materials.
Noise pollution • Install suitable barriers to shield compressors and other small stationary equipment where necessary.
• Display signs to indicate construction activities.
• Maintain all equipment.
• Adhere to provisions of Noise
Prevention and Control Rules 2005, Legal Notice No. 24 regarding noise limits at the workplace as well as NEMA
Noise Excessive Vibration Pollution
Control Regulations, 2000.
Public health, occupational health and safety
• Train staff/workers on occupational health and safety.
• Provide full protective gear and workmen’s compensation cover in addition to the right tools and operational instructions and manuals during construction.
• Design of sewerage system should be as provided in the plans and should be constructed to approved size and design, standard and of approved materials.
• Ensure use of standard construction materials and to the specifications. Avoid undesirable, substandard, hazardous or unauthorized materials during construction and maintenance.
• Sensitized staff on social/health issues such as drugs.
Road traffic disruption
• No overloading of trucks and good driving practices to be practiced.
• Suitable junction/access point to be provided.
• Use of appropriate and legible signage.
• Employment of formal flagmen/women to ensure the public safety.
Insecurity • Provision of security guards, CCTV cameras, security lights and other security apparatus during the entire project cycle.
• Construction work timings shall only in line with the NEMA licensing conditions.
Impacts Proposed Mitigation Measures
Increased water usage
• An alternative water source shall be provided. The proponent shall drill a borehole at the proposed site.
• Management of water usage. Avoid unnecessary wastage.
• Recycling of water at the construction phase where possible.
• Make use of roof catchments to provide water i.e. for general purpose.
Increased waste generation
• Adopt waste minimization at source.
• Monitoring the fate of disposed wastes to ensure they are legally land filled at a recognized controlled site.
• Adhering to Waste Management
Regulations, 2006.
The full report of the proposed project is available for inspection during working hours at:
(a) Principal Secretary, Ministry of Environment and Forestry, NHIF Building, Community, P.O. Box 30126–00100, Nairobi.
(b) Director-General, NEMA, Popo Road, off Mombasa Road, P.O. Box 67839–00200, Nairobi.
(c) County Director of Environment, Nairobi City County.
The National Environment Management Authority invites members of the public to submit oral or written comments within thirty (30) days from the date of publication of this notice to the
Director-General, NEMA, to assist the Authority in the decision making process regarding this plan.
MAMO B. MAMO, Director-General, MR/6533491 National Environment Management Authority.
Dated the 18th October, 2024.
MAMO B. MAMO,
Director-General, National Environment Management Authority.
Extracted Entities (1)
previous_gazette_ref
13554
Details
- Act / Legislation
- THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
- Reference
- No. 8 of 1999
- Section
- section 59
- Signed By
- MAMO B. MAMO
- Title
- Director-General, National Environment Management Authority
- Ministry
- Ministry of Environment And Forestry
- Date Signed
- 18th October 2024
- Page
- 53
- Extraction Method
- regex
Source Gazette
Vol. CXXVI No. 172