APPLICATION FOR LICENCES
100% confidence
via regex
GAZETTE NOTICE NO. 16247
GAZETTE NOTICE NO. 16247
THE ENERGY ACT
(No. 1 of 2019)
APPLICATION FOR LICENCES
PURSUANT to Statutory Instruments Act No. 23 of 2013 of the Energy and Petroleum Regulatory Authority wishes to publish the enlisted regulations in the Kenya Gazette for public comments
Citation
These Regulations may be cited as the Energy (Electricity Supply and Installation Work) Regulations, 2024.
Interpretation
1. In these Regulations, unless the context otherwise requires ―
“Act” means the Energy Act, No. 1 of 2019;
“Advanced consumer installation training” means a training course covering design, installation, testing, commissioning, repair and maintenance at consumer installations for systems supplied and metered at high voltages exceeding 33,000V.
“Advanced power line construction training” means a training course covering design, installation, testing, commissioning, repair and maintenance of power supply lines and equipment for high voltages
“Application” means a formal request to carry any undertaking to generate, export, import, transmit, distribute, or retail supply of electrical energy. It includes a formal request for a licence to carry out electrical installation work;
“Area of supply” shall have the meaning assigned to it under the Act;
“Authority” means the Energy and Petroleum Regulatory Authority established under section 9 of the Act;
“Basic consumer installation training” means a training course covering design, installation, testing, commissioning, repair and maintenance at consumer installations for systems supplied and metered at voltages not exceeding 1,000V.
“Basic power line construction training” means a training course covering design, installation, testing, commissioning, repair and maintenance of power supply lines and equipment for voltages not exceeding 1,000V
“Building” has the meaning assigned to it under the Act;
“Cabinet Secretary” means the Cabinet Secretary for the time being responsible for energy;
6th December, 2024 THE KENYA GAZETTE
“Capital contribution” means that amount of money paid to a licensee, by a person who applies to be connected to a transmission or distribution system, as a contribution to the cost of erecting electric supply lines which enable supply to other persons;
“Connection Charge” means the costs incurred in the development of the infrastructure to connect the customer’s premises;
“Connection service provider” means a transmission, distribution or retail supply licensee;
“Consumer” shall have the same meaning as assigned in the Act;
“Consumer Premises” means the locations where electrical energy is consumed, such as residential homes, places of public entertainment, commercial buildings, or industrial facilities.
“Day” means a calendar day;
“Distribution system” shall have the same meaning as assigned in the Act;
“Electric supply line” shall have the same meaning as assigned in the Act;
“Electrical contractor” means a person licensed by the Authority under Regulation 7 of these Regulations to carry out electrical installation work as specified in the license;
“Electrical installation” shall have the meaning assigned under the Act;
“Electrical installation licence” means a document issued by the Authority under Regulations 6 or 7 of these Regulations, respectively, authorizing a person to carry out electrical installation work either individually or as a body corporate or incorporate for voluntary, business, training, or teaching purposes either for gain or reward or for no charge at all;
“Electrical Installation Licensee” means a licensed electrical worker or electrical contractor.
"Electrical installation work" means the work of installing, altering, or adding to an electrical installation and the supervision of such work;
“Electrical worker” shall have the meaning assigned under the Act;
“Electricity supply system” means any system used to provide a supply of electricity and includes the national grid, mini grids or stand-alone power systems, stand-by auxiliary power supply systems;
“Equipment or appliance” shall have the meaning assigned to it under the Act;
“Form of Contract” means the supply agreement document between the service provider and the consumer as approved by the Authority setting out the rights and responsibilities;
“Grid” shall have the meaning assigned to it under the Act;
“Grid Code” means the document (or set of documents) that legally establishes technical and procedural obligations and other requirements for the connection to and use of an electric power system in a manner that will ensure coordinated, efficient, reliable and safe operations as prescribed in the regulations relating to reliability and quality of supply and service.
“Installation” shall have the meaning assigned to it under the Act;
“Intermediate consumer installation training” means a training course covering design, installation, testing, commissioning, repair and maintenance at consumer installations for systems supplied and metered at voltages not exceeding 33,000V.
“Intermediate power line construction training” means a training course covering design, installation, testing, commissioning, repair and maintenance of power supply lines and equipment for medium voltages not exceeding 33,000V
"Kenya Standard" means a specification or code of practice declared by the Council under the Standards Act;
“Licence” shall have the meaning assigned to it under the Act;
“Licensee” Means a licensed Electrical Worker or Contractor
“Licence Applicant” means a person or business entity which submits an application for an initial or a renewal of licence under these
Regulations;
“Line conductor” means an electrical conductor or cable used for conveying electrical energy and includes so much of any service line as may be placed above ground and in the open air;
"Meter" shall have the meaning assigned to it under the Act;
“Mini grid” means any electricity supply system with or without its own power generation capacity, supplying electricity to more than one
Consumer and which can operate in isolation from or be connected to a third party’s Distribution Network with an installed capacity of up to 1 MW;
“Overhead conductor” means any conductor of an overhead electric supply line normally in tension (charged) and includes line conductors, together with joints and jointing devices used therewith;
“Overhead line” means any electric supply line which is placed above ground and in the open air;
“Places of Public Entertainment” means a building or place used or intended to be used for conducting public entertainment or a public meeting such as schools, airports, transport terminus, conference halls, cinema halls, theatres, clubs and bars.
“Person” shall have the meaning assigned to it under the Act;
"Power system" shall have the meaning assigned to it under the Act;
“Premises” shall have the meaning assigned to it under the Act;
“Revocation” means a licence has been permanently canceled and cannot be reinstated.
“Service line” shall have the meaning assigned to it under the Act;
THE KENYA GAZETTE 6th December, 2024
“Specialized electrical installation work” means works carried out by specialized skilled persons in electrical engineering gained mainly through practical experience such as installation of lifts and escalators, electrical vehicle charging infrastructure, generators, construction of power lines and electrical installations in hazardous environments.
"Specification" has the meaning assigned to it in the Standards Act;
“Stand-alone power system” means an electricity supply system which is not connected to the Grid;
“Supervision” in relation to electrical installation work, means that the work is undertaken under such control and direction of a person authorized under the Act;
"Supply" in relation to electricity, means the sale of electricity to a licensee or consumer;
“Suspension” means a licence is temporarily out of service and can be reinstated upon satisfying set out conditions.
“Underground line” means any electric supply line which is placed underground; and
"Use of electrical energy" means the conversion of electrical energy into chemical energy, mechanical energy, sound, heat or light, or the use or application of electrical energy to or for any of the purposes for which it may be or become or be found to be adapted;
"Voltage" means the effective difference of electrical potential between any two conductors, or between a conductor and the earth, and is said to be—
(a) low when it does not exceed 1,000 volts under normal conditions, subject however to the percentage variation allowed by any regulations made under the Act;
(b) medium when it exceeds 1,000 but does not exceed 33,000V under normal conditions, subject however to the percentage variation allowed by any regulations made under the Act; and
(c) high when it normally exceeds 33,000V under normal conditions, subject however to the percentage variation allowed by any regulations made under the Act;
“Works” shall have the meaning assigned to it under the Act.
In these Regulations, unless the context otherwise requires-
(i) any reference to a numbered Regulation or Schedule is a reference to the Regulation or Schedule bearing that number in these
Regulations;
(ii) any reference to a numbered Sub-regulation is a reference to the Sub-regulation bearing that number in the Regulation in which the reference occurs;
(iii) words importing the singular include the plural and vice versa; and words importing a gender shall include any gender.
Purpose
The purpose of the Regulations is to promote safe use of electrical energy by enforcing quality and safety standards throughout the electricity supply value chain.
Application
These Regulations shall apply to any person carrying out or intending to carry out transmission, distribution, retail supply and use of electricity or any work relating thereto, including―
(i) Planning, construction, operation and maintenance of electric supply lines
(ii) Connection of any premises to an electricity supply system.
(iii) Electrical installation work at the premises of any consumer.
PART II––LICENSING OF ELECTRICAL WORKERS AND CONTRACTORS
General Provisions
A person planning, building, operating or maintaining a transmission or distribution system shall ensure that such works are carried out by a licensed electrical contractor(s) and electrical worker(s) in accordance with Section 151 of the Act.
An owner or occupier of any premises shall ensure that electrical installation work in their premises is—
(a) Carried out by an electrical contractor and commencement of work notice and completion certificates issued to the Connection Service
Provider before connection to supply of electricity.
(b) Tested and inspected periodically, and any defects remedied, as provided in these Regulations.
The Connection Service Provider shall not connect or continue supply to premises where the electrical installation does not meet the conditions set out in sub-regulation (2).
Licensing of electrical workers
A person shall not construct, operate, maintain, inspect or repair electric installation as an electrical worker unless licensed by the Authority:
Provided that the person may carry out such works under supervision of a licensee under these Regulations.
A person who intends to construct, operate, maintain, inspect, or repair an electrical installation as an electrical worker shall make an application to the Authority in accordance with regulation 8.
The Authority may, on receipt of an application for an electrical worker licence, grant the applicant one of the classes of licences set out in the
First Schedule:
Licensing of electrical contractors
A person shall not construct, operate, maintain, inspect, or repair an electrical installation as an electrical contractor unless licensed by the
Authority. The application for an electrical contractor licence shall be in accordance with regulation 8.
6th December, 2024 THE KENYA GAZETTE
The Authority may, on receipt of an application for an electrical contractor licence, grant the applicant one of the classes of licences set out in the
First Schedule:
A holder of an electrical contractor licence shall be required to hold or to have in his employment an electrical worker of the class applied for.
The employment contract for the electrical worker shall be in writing and shall comply with applicable Kenyan Laws.
Where a business has more than one branch, separate licence shall be effected in respect of each branch.
The Authority shall not licence any electrical contractor who is unable to satisfy it that he carries on a business at premises constituting a permanent address.
Application for licences
An application for grant of a licence under these Regulations shall be made online or in any other manner the Authority may, from time to time determine.
The application in sub regulation (1) shall be accompanied by the documentation set out in the Second Schedule, and proof of payment of the relevant fee as set out in the Third Schedule.
A person who wishes to be licensed as an electrical worker or electrical contractor shall make an application, as applicable, in the form set out in the Fourth Schedule.
The Authority or its agent shall examine an application in such a manner as it may determine for the purpose of ascertaining the licence applicant’s qualification and suitability for grant of a particular class of licence.
The Authority shall process the application and communicate the outcome to the applicant in writing no later than —
(a) sixty days from the date of receipt of an electrical worker’s licence application or upgrade of an electrical worker’s licence; and
(b) thirty days from the date of receipt of a licence application for an electrical contractor licence; and
(c) thirty days from the date of receipt of an application for the renewal of a licence under these Regulations.
Where the licence applicant satisfies the requirements under these Regulations, the Authority shall issue the applicant with a licence as set out in the First Schedule.
Validity of Licences
A licence under these Regulations shall be valid for a period of three years as provided under Section 150 (3) of the Act subject to the payment of the annual licence fee provided in the Third Schedule.
Renewal of a Licences
An application for renewal of a licence under these Regulations shall be made online, or in any other manner as the Authority may, from time determine, in the form set out in the Fourth Schedule, and in any event, at least thirty days before expiry of the licence.
The application shall be accompanied by the documentation set out in the Second Schedule and proof of payment of the annual fees as specified in the Third Schedule.
An electrical worker renewing their licence shall be required to obtain at least ten credit points through continuing professional development as set out in the Fifth Schedule, in accordance with subsection 149(3) of the Act.
The Authority shall process a renewal application and communicate the outcome to the applicant in writing no later than thirty days from the date of receipt of the application.
A licensee may before expiry of the licence apply to the Authority in writing for deferment of the licence.
The Authority shall consider the deferment application and accept or reject with reasons in writing within thirty days of receipt of the deferment application.
Subject to sub-regulation 6, any electrical worker licence which is not renewed one year after expiry shall be deemed to have been revoked and shall not be considered for renewal.
Upgrade of licences
An electrical worker who wishes to upgrade a licence shall make an application to the Authority in the form set out in the Fourth Schedule.
The licensee may apply to upgrade to a higher class of licence after three years of issuance of the current licence or upon attaining qualifications meeting the minimum requirements for the higher class of licence.
The Authority shall approve the upgrade of an electrical worker’s licence where the worker has met the required academic and professional qualifications, and job experience as set out in the Second Schedule.
The Authority shall approve the upgrade of an electrical contractor licence where the electrical contractor demonstrates that he has in his employment, a licensed electrical worker equivalent to the class of licence for which the upgrade is required.
The upgrade of a licence shall be subject to the licensee paying the applicable licence fee for the class of licence applied.
Replacement of a licence
Where a licensee demonstrates to the Authority that a licence issued under these Regulations has been defaced, destroyed, or lost, the Authority may, on payment of the fees prescribed in the Third Schedule, issue a duplicate licence.
An application for replacement of a licence under sub regulation (1) shall be in the form set out in the Fourth Schedule, as applicable, and shall be accompanied by the supporting documentation specified in the Second Schedule.
Suspension and revocation of licence
The Authority may suspend or revoke any licence issued under these Regulations where it is satisfied that a licensee has breached these
Regulations, or any conditions attached to the licence.
THE KENYA GAZETTE 6th December, 2024
The Authority shall give a notice of not less than thirty days to the licensee requiring him or her to show cause as to why the licence should not be suspended or revoked. The notice to show cause shall set out the specific areas of non-compliance.
Where a licensee fails to show cause as to why the licence should not be suspended or revoked within the time specified, the Authority may suspend or revoke the licence.
Upon the suspension of a licence, the Authority shall specify in writing the conditions and period of suspension.
A licensee shall, within fourteen days after receiving a copy of the order of suspension or revocation, return the licence to the Authority.
Register of licensees
The Authority shall maintain and publish on its website, a register of all licensed electrical workers and contractors in the form set out in Sixth
Schedule.
PART III––CONNECTION TO AN ELECTRICITY SUPPLY SYSTEM
Duty to provide electricity in area of supply
A Connection service provider shall provide electrical energy appropriate for each category of consumers in its area of supply in accordance with applicable contracts.
In providing electricity to consumers, the connection service provider shall prioritize safety of people and property, protection of the environment as well as sustainability, efficiency and reliability of the supply.
A connection service provider shall prepare and submit to the Authority for approval the Form of Contract to be entered into between itself and its consumers at least once every three (3) years.
The Authority shall process the Form of Contract in sub regulation (3) and communicate the outcome within sixty days of receipt.
Provision of electric supply lines
An electricity supply system to supply consumers may be constructed at the cost of the connection service provider, the national or county governments or by way of capital contributions made by consumers. The electricity supply system shall be owned, operated and maintained by the
Connection Service Provider responsible for the supply area.
A person may use the electricity supply system owned by a connection service provider, subject to the Form of Contract in Regulation 15 being approved by the Authority and in accordance with Section 140 of the Act, and the Grid Code.
Application for connection to an electric supply system
A person requiring connection to an electricity supply system, for any purpose, shall apply to the Connection Service Provider in charge of the supply area as set out in the Seventh Schedule.
The Connection Service Provider shall prominently display on its website and at all offices where an application for connection may be made, the complete list of documents to be furnished with each application and the procedure for processing the application.
Application for new connection shall be made in the form prescribed by the Connection Service Provider and any error, omission or defect in the application shall be communicated to the applicant in writing within fourteen days of receipt of the application.
Upon application by any person, the Connection Service Provider shall, in accordance with Regulations 20, notify the applicant in writing of the terms and conditions to be complied with before connection is made.
Records and costs of connections
A Connection Service Provider shall maintain records of all persons:
(a) that apply for electricity connection, including their identification details, connection details, date of application and of connection, thereof;
(b) whose premises get connected to electricity supply system within their area of supply together with costs of all electric supply lines erected to enable the connections and the capital contributions thereof; and
(c) Whose connection applications are declined and the reasons thereof.
A Connection Service Provider shall carry out an annual analysis of all new connections made at each supply voltage in that year and derive the average costs of single and three phase connections. This analysis shall be submitted to the Authority within three months of the start of the subsequent financial year.
Charges for connection
A Connection Service Provider shall provide the consumer with a connection charge based on a methodology approved by the Authority.
Where a consumer opts to pay for the extension of an electricity supply line, the licensee shall conduct a comprehensive design to determine the number of other persons that may use the line in future. The capital contribution of the consumer shall be shared based on the estimated number of persons identified in the design.
The Connection Service Provider shall share the design and estimated number of other persons that may use the electricity supply in future before making the consumer makes a capital contribution. Where the consumer agrees with the estimate, the consumer and Connection Service provider shall enter into a reimbursement agreement in the form approved by the Authority.
Future consumers connected to the service line shall be required to pay their estimated share of capital contribution as part of the connection charges to the licensee which shall be transferred to the contributor until the amount is fully recovered.
Reimbursable costs in sub regulation (3) shall not include the cost of the service line, the cost of the meter and a dedicated line.
The Connection Service Provider should clearly display in its website and offices, the approved connection charges for single and three phase supply taking into account the meter, service line and associated accessories.
Terms and conditions for connection
6th December, 2024 THE KENYA GAZETTE
Upon receipt of any application for connection to any electricity supply system, the Connection Service Provider shall:
(i) make a determination of the connection charges in accordance with the approved methodology in Regulation 19.
(ii) establish all persons who may have made capital contributions in respect of the electric supply system that the applicant is to be connected to and any refunds due to those persons;
(iii) advise the applicant the payments to be made before the connection is made, as well as any refunds that the applicant may be entitled to from persons that may be subsequently connected to the electric supply system for which he has made a capital contribution.
The payments and refunds contemplated in sub regulation (1) shall be determined in accordance with the approved methodology in Regulation
19.
Customer Service Charter
A connection service provider shall establish a Customer Service Charter to be approved by the Authority upon grant of license. The Customer
Service Charter shall at a minimum include details set out in the Eighth Schedule.
The Customer Service Charter in sub regulation (1) shall be valid for the Tariff Control Period as prescribed in section 165 (7) of the Act.
Other connection requirements
The connection to an electricity supply system shall further be informed by the provisions of the Connections Chapter of the Grid Code.
A consumer shall pay on demand, charges for consumption of electrical energy, whether such charges are due to the licensee for the supply of electrical energy to the premises in respect of which such supply is demanded or in respect of other premises metered by the same customer.
A licensee may require a consumer to make meter and account deposits as shall be contained in the methodology approved by the Authority.
Metering
A Connection Service Provider shall establish a meter reading cycle for purposes of ascertaining the charges for consumption of electrical energy.
Provided that a consumer may with the agreement of the Connection Service Provider take the readings in the meter and submit the same for billing purposes.
Meters for measuring electrical energy shall be located outside the consumer’s premises where the Connection Service Provider can easily access and at a height of not more than two metres from the ground. For the purposes of this Regulation the term “outside” means at the exterior of the perimeter wall of the customer’s premises or exterior of the consumer premises.
The security of the energy meter shall be the responsibility of the consumer upon whose premises the meter was placed in accordance with section 155 of Act.
PART IV–– CONSUMER INSTALLATIONS
Electrical installation in the premises of a consumer
A Licensee under these Regulations shall carry out electrical installation works to meet the requirements of the applicable Kenyan laws, codes, standards and guidelines. The materials used for electrical installation conform to the relevant Kenya Standards.
A Licensee shall, prior to any electrical installation, be required to issue to the premise owner or occupier, a commencement of work notice in
Form 004 set out in the Ninth Schedule. Where there is change of the Licensee undertaking the installation, a fresh commencement of work notice shall be required.
Upon conclusion of electrical installation works, a Licensee shall:
(i) Carry out electrical inspections and tests and issue a certificate of completion in Form 005 set out in Ninth Schedule to the premises owner or occupier.
(ii) Issue ‘as built’ schematics and drawings to the premises owner or occupier.
(iii) train the premises owner or occupier on basic operating procedures for the installation and provide user manuals where applicable.
Commencement of Work and Completion of Work Certificates shall be generated by Electrical Contractors licensed under these Regulations in a manner prescribed by the Authority and shall be signed by the electrical worker in charge of the installation.
Where the Connection Service Provider notices from the Certificate of Completion and test records that an electrical installation does not meet the requirements, the Licensee shall make good the defects at his own costs.
Where the Licensee fails to make good the defect noticed under sub regulation (5), his licence shall be liable for suspension or revocation by the
Authority.
Inspection of Electrical installation at the Premises of a Consumer by the Connection Service Provider
The Connection Service Provider shall be required to undertake inspection of the electrical installations at the supply connection point before connecting the premises to supply.
Where upon inspection of the electrical installation at the premises of a consumer, the Connection Service Provider is reasonably satisfied that-
(i) the wiring or fittings are not suitable for the service voltage;
(ii) a defect exists at some part of the circuit of such extent as to be a source of danger; or
(iii) any other requirements of these Regulations are not being complied with;
The Connection Service Provider shall not commence supply or shall discontinue the supply of electrical energy to the consumers’ terminals and shall give immediate Defective Installation Notice as set out in the Tenth Schedule to the consumer indicating the reason for not giving, maintaining or restoring the supply.
The cost of the initial inspection in sub-regulation (2) shall be borne by the Connection Service Provider. Where defects have been identified, the costs for each subsequent re-inspection shall be borne by the electrical contractor who issued the Certificate of Completion at a rate approved by the
Authority.
THE KENYA GAZETTE 6th December, 2024
Notwithstanding the inspection and testing by the Connection Service Provider, the Connection Service Provider shall bear no responsibility for any loss or damage arising out of the commencement of supply.
Periodic testing and inspection of electrical installations
The owner or occupier of any building or premises shall cause periodic inspection and testing of the electrical installation of their building or premises to be conducted to ascertain that the installation is in good condition and safe. The periodic inspections and tests shall be conducted at intervals set out in the Eleventh Schedule.
The periodic tests and inspections shall be carried out by a person licensed under these Regulations. The Licensee shall issue to the owner or occupier of the premises—
(i) an inspection and test report; and
(ii) Periodic inspection and test certificate in Form 007 as set out in Twelfth Schedule.
(iii) The inspection and test certificate shall be displayed at the electricity supply point or meter box for the building or premises.
The Connection Service Provider shall issue a defective installation notice to the owner or occupier of any building or premises which is overdue for periodic inspection and testing. If the defect is not rectified within the period specified in the notice, the Connection Service Provider may discontinue the supply until this regulation is complied with.
Notwithstanding the conditions in sub-regulation (4), owners or occupiers of premises not connected to any Connection Service Provider shall be required to comply with sub-regulation (1), (2) and (3)
PART V––ELECTRIC SUPPLY SYSTEMS
Construction and maintenance of overhead and underground supply lines
A licensee shall carry out construction and maintenance of overhead and underground transmission and distribution lines in accordance with applicable Kenyan codes, standards and guidelines issued by the Authority. The materials used for electrical installation shall conform to the relevant Kenya Standards.
A licensee shall not construct or maintain any overhead and underground lines without the necessary permits, approvals and way leave consent.
A Licensee shall take responsibility for any incident or accident that occurs during construction of power supply lines unless proven that the accident was inevitable or as a result of force majeure.
Upon conclusion of construction of overhead or underground supply lines, the licensee shall:
(i) carry out electrical inspections and tests and issue a Certificate of Completion in Form 006 set out in Ninth Schedule. The Certificate of
Completion shall be issued to the Connection Service Provider or the power line operator.
(ii) issue ‘as built’ schematics and drawings to the Connection Service Provider or the power line operator.
Where the Connection Service Provider notices from the Certificate of Completion and test records that a power supply line installation does not meet the requirements, the licensee shall make good the defects at his own costs.
Where the licensee fails to make good the defects identified under sub-regulation (5), his licence shall be liable for suspension or revocation by the Authority.
PART X––MISCELLANEOUS PROVISIONS
Offences, Fines and Penalties.
A person who commits the offences set out in the Thirteenth Schedule of these Regulations, shall be liable to the penalties set out therein.
The penalties in these Regulations are without prejudice to the Authority’s right to suspend or revoke a licence.
The payment of a fine shall not indemnify an electrical worker or contractor from any obligations to compensate the aggrieved party.
Any fine which is not paid shall be a civil debt recoverable summarily.
Powers to inspect
The Authority or its agents may inspect the premises where an electrical installation is taking place or has been done to ensure compliance with these regulations pursuant to Section 11 of the Act.
Compliance orders
Where the Authority finds that any provision of these Regulations has been contravened by a licensee, Connection Service provider or owner or occupier of premises or that a condition has arisen which may lead to the contravention of these Regulations, the Authority may issue a compliance order compelling the person to comply with the Regulations.
An order issued under this regulation shall state —
(i) the specific provision which has been or is likely to be contravened;
(ii) the specific provision which has been or is likely to be contravened;
(iii) the measures which should be taken to rectify the contravention; and
(iv) the period within which the order shall be complied with.
Health, Environmental and Safety Obligations
A licensee shall comply with the provisions of the applicable environmental, health and safety laws.
Handling of Complaints, Disputes and Appeals
Any complaints and/or disputes between any party and a Licensee or between two or more licensees shall be referred to the Authority for resolution in accordance with the Act and relevant regulations.
6th December, 2024 THE KENYA GAZETTE
Any person aggrieved by a decision or order of the Authority may appeal to the Tribunal in accordance with section 24 of the Act.
Local Content
A licensee or Connection Service Provider under these Regulations shall comply with local content requirements in accordance with the provisions of section 206 of the Act.
Insurance against injury to persons and damage to property
Licensed electrical contractors shall maintain such insurances as necessary to cover injury and damage to property including damage to the works arising out of or in the course of or by reason of carrying out the electrical works.
PART XI––REVOCATION, SAVINGS AND TRANSITIONAL PROVISIONS
Revocation
The Electric Power (Electrical Installation Works) Rules, 2006, are revoked.
Preservation of Licences and Certificates
Any person certified or licensed under the Electric Power (Electrical Installation Works) Rules, 2006 (now repealed) shall carry on as though certified or licensed under this Regulations, without having to apply for new licence, and shall enjoy all rights and privileges as provided under these
Regulations. Provided upon expiry of the existing license, the same shall be renewed under these Regulations as below.
(i) A-1 becomes class A
(ii) B becomes class B
(iii) C-1 becomes class C
(iv) C-2 becomes class D
(v) A-2 becomes class L or G2 as applicable
Continuance of periods of time
Where a period specified in the repealed Rules is current at the commencement of this Regulations, this Regulations shall have effect as if the corresponding provisions had been in force when the period began to run.
FIRST SCHEDULE [r.6(3), 7(2), 8(6)]
CATEGORIES AND CLASSES OF LICENCES
CONSUMER INSTALLATIONS CATEGORY
Licence
Class
Scope of Work
A Shall entitle the holder to carry out all kinds of electrical installation work in consumers’ premises for connection to supply metered at any voltage except for specialized electrical installation work.
B Shall entitle the holder to carry out electrical installation work in consumers’ premises for connection to supply metered at voltages up to 33,000 Volts except for specialized electrical installation work.
C Shall entitle the holder to carry out electrical installation work in consumers’ premises for connection to a single and/or three phase supply metered at voltages not exceeding 1000 Volts except for specialized electrical installation work.
D Shall entitle the holder to carry out electrical installation work in consumers’ premises for connection to a single-phase supply metered at voltages not exceeding 1000 Volts except for specialized electrical installations.
SPECIAL INSTALLATIONS CATEGORY
G G 1: Shall entitle the holder to carry out electrical installation works, tests and inspections for electric power generators of all capacities at consumer premises
G 2: Shall entitle the holder to carry out electrical installation work, tests and inspections for electric power generators at consumer premises of capacity not exceeding 500KVA
L Shall entitle the holder to carry out electrical installation work for lifts and escalators.
EV Shall entitle the holder to carry out electrical installation work for electric vehicles (EV) charging infrastructure.
H H1: Shall entitle the holder to carry out electrical installation work for hazardous or potentially explosive areas such as filling stations, chemical plants and fuel depots.
H2: Shall entitle the holder to carry out electrical installation work for hazardous or extreme temperatures areas such as data center, incinerators, cold rooms, boiler rooms and swimming pools including saunas.
P P1: Shall entitle the holder to work on electric supply lines of voltages exceeding 33000V and the works defined in P2.
P2: Shall entitle the holder to work on electric supply lines of voltages not exceeding 33000V and the works defined in P3.
P3: Shall entitle the holder to work on electric supply lines of voltages not exceeding 1000V including streetlights.
SECOND SCHEDULE [r. 8(2), 10 (2), 11(2), 12(2), ]
MINIMUM LICENSING REQUIREMENTS
Licensing Requirements for Electrical Contractor Licence
New Licence Applications Requirements
(i) Duly filled application form documenting all requirements.
THE KENYA GAZETTE 6th December, 2024
(ii) Application fees
(iii) Certified copy of the certificate of incorporation or business registration certificate.
(iv) Certified copy of Form CR 12 from the Registrar of Companies.
(v) Certified copies of identification documents (National Identification Card or Passports) for all the company's directors.
(vi) Certified copy of a valid Work Permit Class "G" for foreign directors working in Kenya or notarized declaration of non-residence for foreign directors not residing in Kenya.
(vii) Certified copy of a valid Trading Licence/ Single Business Permit from the County Government.
(viii) Copy of a valid KRA Tax Compliance Certificate.
(ix) Adequately equipped office premises
(x) Proof of occupancy of the applicant’s office.
(xi) Duly executed employment contract between the electrical contractor and electrical worker attested by a commissioner for oaths/notary public clearly indicating the engagement period and other terms of employment as stipulated in Sub regulation 7(4).
(xii) List of electrical test instruments and equipment as set out in the table below
CONSUMERS’ INSTALLATIONS CATEGORY
Class Tools and equipment Class Tools and equipment
A, B & C 1 Phase rotation meter
2 Insulation resistance tester
3 Earth resistance tester
4 Earth loop impedance tester
5 Multimeter/Clamp meter
6 Personal Protective Equipment
Well-stocked electrician toolbox
D 1 Insulation resistance tester
2 Earth resistance tester
3 Earth loop impedance tester
4 Multimeter/Clamp meter
5 Personal Protective Equipment
6 Well-stocked electrician toolbox
ELECTRIC SUPPLY LINES CATEGORY
Class Tools and equipment Class Tools and equipment
P2 and P3 1 Materials transportation equipment.
2 Tower/Pole erection equipment, 3 Tower/Pole climbing tools, 4 Conductor stringing, sagging and tensioning equipment
5 Rigging tools and equipment;
6 Electrical test equipment;
7 Personal Protective Equipment
Well-stocked electrical lineman toolbox
P1 1 Materials transportation equipment.
2 Excavation equipment;
3 Pole erection equipment, 4 Pole climbing tools, 5 Conductor stringing, sagging and tensioning equipment
6 Rigging tools and equipment;
7 Electrical test equipment;
8 Personal Protective Equipment
9 Well-stocked electrical lineman toolbox
SPECIAL INSTALLATIONS CATEGORY
Class Tools and equipment
EV, H, G, &L
1 Phase rotation meter
2 Insulation resistance tester
3 Earth resistance tester
4 Earth loop impedance tester
5 Multimeter/Clamp meter
6 RCD (safety switch) tester
7 Well-stocked electrician toolbox
A.2 Renewal Licence Application Requirements
1. Duly filled application form documenting all requirements.
2. Licence renewal fees
3. Valid tax compliance certified
4. Valid trading licence/Single business permit
5. Active electrical worker licence
6. Electrical worker consent or employment letter
6th December, 2024 THE KENYA GAZETTE
Qualification Criteria for Electrical Worker Licence
1: New Licence Applications Requirements
1. Duly filled application form documenting all requirements.
2. Licence application fees
3. Copy of national identification card.
4. Passport photograph
5. Copies of academic and professional certificates (minimum qualifications are as set out in table B.1.1, B.1.2 and B.1.3).
6. To undergo competency assessment test/examinations.
B.1.1: Consumer Installations Workers
Licence Class Minimum Academic
Qualification Professional Qualification Electrical Installation Experience
Highest
Achievable
Licence Class
Class A KCSE or Its
Equivalent
• Bachelor degree in
Electrical Engineering
1. At least three (3) years of electrical installation experience working on consumers’ premises OR Two
(2) years electrical installation experience working on consumers’ premises with Advanced Consumer
Installation training from an accredited institution
2. At-least three verifiable electrical installation projects in consumer premises supplied at 33KV
A
Upgrading from class B after three years of verifiable practice with class B license
Class B KCSE or its equivalent
Higher Diploma in Electrical
Engineering or Degree in
Electrical technology
1. At least three (3) years of electrical installation experience working on consumers’ premises or Two
(2) years electrical installation experience working on consumers’ premises with Advanced Consumer
Installation Training from an accredited institution.
2. At-least three verifiable electrical installation projects in consumer premises supplied at medium voltage working under a licensed class B or higher electrical contractor.
A
Upgrading after three years of verifiable practice with C
Licence.
Class C KCSE or its equivalent
Diploma in Electrical
Engineering
1. At least two (2) years electrical installation experience working on consumers’ premises supplied at voltages not exceeding 1,000V or One (1) year electrical installation experience working on consumers’ premises with a Intermediate
Consumer Installation training from an accredited institution.
2. At least three verifiable projects on consumer premises supplied at voltages not exceeding 1,000V working under a licensed class C or higher electrical contractor.
B
Upgrading from class D after three (3) years of verifiable practice with class D license
Class D KCSE or its equivalent
Electrical Artisan, Trade Test
Grade II, Craft certificate
1. Two (2) years of electrical installation experience working on consumers’ premises supplied at 240V or
One (1) years electrical installation experience working on consumers’ premises supplied at 240 V with an Basic Consumer Installation Training from an accredited institution
2. At-least three (3) verifiable electrical installation projects on consumer installations supplied at 240
Volts
C
B.1.2. Special Electrical Installation Workers
Licence Class Minimum Academic
Qualification
Professional Qualification and
Experience Installation Experience
Highest
Achievable
Licence Class
G G1 KCSE or its equivalent
Diploma/degree (in Electrical engineering, Electrical
Engineering Technology or mechatronic engineering)
1 Training in Generator installation and
Maintenance.
2 Verifiable two years’ experience working on generators of rating exceeding 500kVA at consumers’ premises.
G1
Upgrading from class G2 after three (3) years of verifiable practice with class G2 license
G2 KCPE or its equivalent
Electrical Craft, Artisan, Trade
Test Grade II, Diploma or degree in Electrical
/mechatronic Installation
Technician II and any
1 Training in Generator installation and
Maintenance.
2 Verifiable two years (2) work experience working
G1
THE KENYA GAZETTE 6th December, 2024
B.1.1: Consumer Installations Workers
Licence Class Minimum Academic
Qualification Professional Qualification Electrical Installation Experience
Highest
Achievable
Licence Class recognized equivalent. on generators at consumer premises
H H1 KCSE or its equivalent
Diploma/Degree (in Electrical engineering, Electrical
Engineering Technology engineering)
1. Training in electrical installations for hazardous or potentially explosive areas.
2. Verifiable two years (2) work experience working on hazardous or potentially explosive areas.
H1
H2 KCSE or its equivalent
Diploma/Degree (in Electrical engineering) or related equivalent
1. Training in electrical installations for hazardous or extreme temperatures areas
2. Verifiable two years (2) work experience working on hazardous or extreme temperatures areas
H2
L KCPE or its equivalent
Artisan, Trade Test Grade II, Electrical Installation
Technician II, Diploma, or
Degree in
Electrical/Mechatronics and any recognized equivalent.
1 Training in electrical installations for lifts and escalators
2 Verifiable two years (2) work experience working on lifts and escalators.
L
EV KCSE or its equivalent
Diploma/Degree in electrical engineering or degree in electrical engineering technology
1 Training in installation of electric vehicles supply equipment (EVSE) and battery swapping facilities.
2 Verifiable one year (1) work experience working on electric vehicles charging infrastructure.
EV
P P1 KCSE or its equivalent
Diploma/Degree in electrical
/mechanical engineering
1. Verifiable two years (2) work experience in power lines construction for voltages exceeding 33kV and Advanced Power Line Construction Training from an accredited institution
2. At least three verifiable projects done in power line construction at voltages exceeding 33kV
P1
Upgrade after three years verifiable experience with P2
P2 KCSE or its equivalent
Craft/Diploma/Degree in
Electrical or mechanical engineering
1. Verifiable two years (2) work experience in power lines construction for medium voltages not exceeding 33kV.
2. Intermediate Power Line Construction Training from an accredited institution.
P1
Upgrade after three years verifiable experience with P3
P3 KCPE or its equivalent
Electrical or mechanical grade test /Artisan certificate
1. Basic Power Line Construction Training from an accredited institution.
2. Verifiable two years (2) work experience in power lines construction for voltages not exceeding
1000V.
P2
B.2: Renewal Applications Requirements
1. Duly filled application form documenting all requirements.
2. Licence application fees
3. Copy of national identification card.
4. Report of continuing technical trainings and experience.
THIRD SCHEDULE (r. 8(2), r.9, r. 10(2), 1),r. 12(1)]
LICENCE FEES
Table 1. Licence Fees for Electrical Workers
Class of Licence Fees in Kenya Shilling in Respect of
Application for License Fees Annual Licence Fees Three Years Licence Fees Licence Replacement Fees
Class P 1 1000 2,000 6,000 500
Class P 2 1,000 2,000 6,000 500
Class P3 1,000 2,000 6,000 500
Class A 1,000 2,000 6,000 500
Class B 1000 1,000 3,000 500
Class C 500 750 2,250 500
Class D 250 500 1,500 500
Class G1 1,000 2000 6,000 500
Class G 2 1,000 2,000 6,000 500
Class L 1,000 2,000 6,000 500
6th December, 2024 THE KENYA GAZETTE
Class EV 1,000 2,000 6,000 500
Class H1 1,000 2,000 6,000 500
Class H2 1,000 2,000 6,000 500
Table 2. Licence Fees for Electrical Contractors
Class of
Licence
Fees in Kenya Shilling in Respect of
Application for Licence Annual Licence Fees Three Years Licence Fees Licence Replacement Fees
Class P1 1,000 5,000 15,000 1000
Class P2 1,000 5,000 15,000 1000
Class P3 1,000 5,000 15,000 1000
Class A 1,000 5,000 15,000 1000
Class B 1,000 3,000 9,000 1000
Class C 500 2,000 6,000 1000
Class D 500 1,000 3,000 1000
Class G1 1,000 5,000 15,000 1000
Class G2 1,000 5,000 15,000 1000
Class L 1,000 5,000 15,000 1000
Class EV 1,000 5,000 15,000 1000
Class H1 1,000 5,000 15,000 1,000
Class H2 1,000 5,000 15,000 1,000
FOURTH SCHEDULE [r. 8(3),10 (2) 11(1), 12(2)]
LICENCE APPLICATION FORMS
FORM 001: APPLICATION FOR A LICENSE FOR AN ELECTRICAL WORKER
The Director General
Energy and Petroleum Regulatory Authority
P.O. Box 42681– 00100, GPO
Nairobi
I hereby apply to be licensed as a Class ……………… electrical worker in accordance with the Energy (Electricity Supply) Regulations, 2021, and commit to carry out all electrical installation work in compliance with the Energy Act, No 1of 2019 and any Regulations for the time being in force therein.
Name in full……………………………………………………………………………………………..
First Name .............................................................. Middle Name ......................................................................... Surname ................................................
P. O. Box ……………………………………..Postal Code ………………………Town ………………………………..………………………………
Mobile No. …….………….……………………….… Email ……………..……………………………………................................................................
Date of Birth …………………………… ID/Passport No. ………………….…………. Nationality………………………………………………….…
Name and address of present employer, (if any)
………………………………………………………………………………………………………………………………………………………………
Title of present job ……………….………………………………………………………………………………………………………………………...
Experience and Qualifications––
Details of educational qualifications and examinations passed ……………….………………….……………………………………..............................
(b) Details of apprenticeship …………………………………………………………………………………………………………………………...…..
(c) Experience in the work of an electrical worker ……………………………………………………………………………………...…………………
Knowledge of Regulations:
Current Edition of Kenya Wiring Regulations (KS 662) .................................................................. Yes/No ......................................................................
Occupational Health and Safety Act ................................................................................................. Yes/No ......................................................................
The Energy (Electricity Supply) Regulations, 2021 ......................................................................... Yes/No ......................................................................
Details of electrical installation certificate held (if any)
Certificate No……………………………………………………….… Issued on………………..………………………………………………………..
Issued by…………………………………………………………………………………………………………………………………………..……....……….
I have paid Kenya Shillings. ………………………………………………..…. being the application fee.
Payment Reference No………………………………………………………. dated …………………………………………………………...…………
I declare that the particulars given above are true and correct
Signature of Applicant … ……………………………………………………… Date……………..………...………………………………….……….
REFEREES
Provide details of two referees who know your ability in the trade.
THE KENYA GAZETTE 6th December, 2024
1st Referee
Name in full……………………………………………………………………………………………………………………………………………...…
First Name ......................................................................................... Middle Name ................................................. Surname .............................................
P. O. Box ………………………… Postal Code ……………Town ……………………………………………………………...………………………
Mobile No. …….…………………… ID/Passport No. ……………………………………………………………………………………...……………
Electrical installation certificate No. ………………………………………………………………………………………………………………....…….
Position held at present…………………………………………………………..…………………………………………………………………....……
2nd Referee
Name in full……………………………………………………………..………………………………………...………………………………..………
First Name ......................................................................................... Middle Name ................................................. Surname .............................................
P. O. Box ………………………… Postal Code ……………Town ……………..…………………………………………………………..…………
Mobile No. …….…………………… ID/Passport No. …………………………………………………………………………………..……..………
Electrical installation certificate No. ……………………………………………………………………………………………………..……………..
Position held at present…………………………………………………………………………………………………………………..………………
Form 002: Application for a Licence for an Electrical Contractor
The Director General
Energy and Petroleum Regulatory Authority
P.O. Box 42681- 00100, GPO
Nairobi
I/We……………………………………………………………..…………………………………………………………………………..……………… hereby apply to be licensed as a Class ……… electrical contractor in accordance with the Energy (Electricity Supply) Regulations, 2021. I/we intend to conduct the business from premises occupied by me/us and described below:
Description of the premises:
Town………………………………
Location/Road………………………………………………………………………………………..………………
Name of the Building………………………………………………………....……………………………………………………………..………….….
Details of Business
Business registration No. …………………….… and date………………….………………………………………………………………..……………
P. O. Box …………………… Postal Code ……………..Town…………….………………………………………………………………..………….
Telephone/Mobile ………............…………….. Email………………….…………………………………………………………………..…………..
Names of partners / directors, their addresses and nationalities
…………………………………………………………………………………………….………………………………………………………………
Licensed electrical worker(s) who will supervise the electrical installation work:
Full names of electrical worker Certificate No
(1)………………………………………………..……………………… ……………………………………………………………………………..….
(2)……………………………………………….. ………………………………………………………………………………………………..……….
(3)……………………………………………….. ………………………………………………………………………………………………..……….
Previous experience in electrical installation work …………………………………….…………………………………………………………..…….
Name and address of bank(s) or financial institution(s) where the business account(s) is/are maintained
……………………………………………………………………...………………………………………………………………………..……………...
Details of the tools and measuring and testing instruments available:
(a) List of tools
Description of Tools and Equipment
(i) ………………………..…………………………….…….…………………………………………………………………………………..…...……..
(ii) ………………………..……………………….………….………………………………………………………………………………..………..…..
(iii) ………………………..……………………….…………….……………………………………………………………………………..…………...
(b) List of Testing Instruments
Description .......................................................................................................... Make ........................................................ Serial No. ...............................
(i) ………………………..……………………….……..….…………………………………………………………………………………………..…...
(ii) ………………………..…………………….……..……….………………………………………………………………………………..…………..
6th December, 2024 THE KENYA GAZETTE
(iii) ………………………..…………………….……..……….………………………………………………………………………………..………….
(iv) ………………………..…………………….……..………….……………………………………………………………………………..………….
I/We hereby apply for licensing of the above mentioned Electrical Contractor in accordance with the Energy (Electricity Supply) Regulations, 2021 and undertake to carry out all work in strict compliance with the Energy Act No 1 of 2019 and any Regulations for the time being in force thereunder.
Payment Reference No……………………………………. dated ……………….……………
For KShs. ……………………………………………………. being the application fee.
I declare that the particulars given above are true and correct.
Signature of Applicant ……………………………… Date……………………………………………………………………………..…………….
Attach copies of
(i) Business Registration Certificate or Certificate of Incorporation and CR12 (where applicable)
(ii) Licensed Electrical Worker
(iii) Contract with Electrical Worker witnessed and commissioned by a Commissioner for Oath, if applicable
(iv) Office lease agreement or proof of ownership
(v) PIN Certificate
(vi) Valid Business Licence/Permit
(vii) Valid Tax Compliance Certificate
(viii) Route Sketch to your premises.
Form 003: Application for Replacement of Licence
APPLICANT DETAILS
Type of Licence
(Electrical Worker or Electrical Contractor)
Licence Number
Name of Worker/Contractor
Company Registration No. /
National ID No (or passport).
Telephone Number
Email address
Postal Address
REASON FOR REPLACEMENT AND DECLARATION
I ……………………………......................................................…….. do solemnly and sincerely declare that a replacement certificate/licence is required because (state reason for loss ):
………………………………………………………………………..……................................
……………………………………………………………………………………………………..................................................................................
..........................................................................
And I make this solemn declaration by virtue of the Oaths and Statutory Declarations Act (Cap 15 of the Laws of Kenya) and conscientiously believing the statements contained in this declaration to be true in every particular. I acknowledge that a person willfully making a false statement in a statutory declaration is guilty of an offence and is liable to a penalty or imprisonment or both
Declared at (place) ………………………………................. on (date) ……………………….
Signature of Declarant........................................ Signature of Witness...............................….
Name & Phone number of Witness..............................................................................................
.......................................................................................................................................................
Note: This declaration may be witnessed by anyone aged 18 years or over.
Supporting Documents to accompany the application/declaration.
(i) Copy of national identification card or passport (for electrical workers)
(ii) CR12 form that is not more than 6 month old (for electrical contractors)
(iii) Police Abstract
(iv) Evidence of payment of certificate/licence replacement fees
FIFTH SCHEDULE [r.10(3)]
CONTINUING PROFESSIONAL DEVELOPMENT FOR LICENCE RENEWAL
The licensee shall accumulate a minimum 10 points at the expiry of the licence as follows —
THE KENYA GAZETTE 6th December, 2024
1. Attending relevant trainings or seminars or workshops; 1 credit points per training;
2. Providing relevant seminars, training or workshop as a resource person; 1 credit point per training;
3. Presenting a paper on a relevant topic at a conference or publishing a paper in a journal; 1 credit point for each paper;
4. Project credit points earned through experience gained from design, installation, testing and commissioning, operation and maintenance of electrical consumer installations according to the class of licence as follows —
Licence Class Project credit points Voltage Level of Project
A 2 Above 33kV
B 2 1kV – 33kV
C 2 0.240V-33kV
D 2 0.240V
The project credit points shall account for a minimum of eight points up to a maximum of 9 points, and the trainings attended shall account for a maximum of two points.
SIXTH SCHEDULE [r (14)]
FORM OF REGISTER FOR ELECTRICAL WORKERS AND CONTRACTORS
EPRA/ERE/ELEC -3.01
REGISTER OF ACTIVE ELECTRICAL WORKERS AS AT: 06-06-2024
SN Name Licence Class Licence Number County Town Date of Expiry
1.
2.
EPRA/ERE/ELEC -3.02
REGISTER OF ACTIVE ELECTRICAL CONTRACTORS AS AT: 06-06-2024
Electrical Contractor Electrical Worker
SN Name Licence Class Licence Number County Town Name Licence Class Licence Number Date of Expiry
1.
2.
SEVENTH SCHEDULE (r. 17(1))
GUIDELINES FOR NETWORK CONNECTIONS
This Schedule sets out procedures for connecting the premises of any consumer to the distribution or transmission network of any licensee
(hereinafter referred to as the network), for any purpose.
Information to be provided by an applicant
1. (1) A person requiring connection to the network of any Connection Service Provider pursuant to Regulation 17 shall file his application with the Connection Service Provider, detailing the information set out below:
(i) Name and contact details of the applicant.
(ii) Description and address of the premises where connection is required, including a site location plan showing the site boundary and a site layout plan, drawn to a suitable scale.
(iii) A reasonable date by which the connection is required.
(iv) The purpose for which the connection is required, and where applicable, as detailed in the Grid Code.
(v) Any other relevant information as required by the Connection Service Provider to facilitate the connection.
(2) The Connection Service Provider may prescribe the form to be filled by the applicant.
Processing of an application
1. Budget Estimates: If the applicant makes an enquiry of a provisional nature, the Connection Service Provider may provide an indication of the charge for providing the connection in a Budget Estimate. Any estimate that is provided at this stage will be the result of a preliminary assessment only and need not be accepted by the applicant. The budget estimate is not binding on either party.
2. Feasibility Studies: For more complex connections, the Connection Service Provider may at the request of the applicant undertake a feasibility study to consider a number of options for connection and provide budgetary estimates for each option. Any cost estimate at this stage need not be accepted by the applicant
3. Connection Offers: An applicant need not to have requested a Budget Estimate or Feasibility Study before making a request for a
Connection Offer. Upon application for a connection, the request may be dealt with in three key stages set out below:
(i) Stage 1: Upon satisfaction that all the required information has been provided the Connection Service Provider will process the application as set out below.
(ii) Stage 2: The Connection Service Provider shall take into account the location of the premises for which the connection is required, its proximity to the existing network and the available capacity in the network to provide the required connection.
6th December, 2024 THE KENYA GAZETTE
(iii) Stage 3: The Connection Service Provider will issue a formal Connection Offer to the applicant detailing the works to be carried out, connection charges, offer validity period and any other terms and conditions to be fulfilled before the connection is made.
It should be noted that the cost provided by the Connection Service Provider at this stage may vary considerably from any previous budgetary estimate.
EIGHTH SCHEDULE [r.21 (1)]
MINIMUM REQUIREMENTS OF THE CUSTOMER SERVICE CHARTER
The following information shall be contained in the Connection Service Provider’s Customer Service Charter:
1. A comprehensive outline of the different types of electrical connections that the Connection Service Provider offers and a timeframe for when the connection will be made.
2. An outline of the payment terms within which the Customer should pay for the electrical supply.
3. An outline of the obligations of the Connection Service Provider to the customer. This includes information on the quality of electrical energy supply to the customer and the Connection Service Provider's obligations in the event of a planned or unplanned interruption.
4. An outline of the complaints procedures available to the customer.
5. An outline of compensation procedures that shall be followed once a claim for a breach has been made by a Customer.
6. An outline of the customer's obligations in relation to all new connections and the Customers obligations in relation to the maintenance of the connection.
7. An outline of how Customers can provide the Connection Service Provider with feedback and suggestion on the quality of electrical energy supply.
8. An outline of all the Connection Service Provider’s contact information.
NINTH SCHEDULE (r.24 (2), 24(3))
INSTALLATION CERTIFICATES FOR ELECTRICAL INSTALLATIONS AND ELECTRIC POWER LINES
FORM 004: COMMENCEMENT OF WORK NOTICE
FOR CONSUMER INSTALLATIONS AND SPECIAL INSTALLATIONS
No……………………..
To:
………………………………………………………………………………………….
………………………………………………………………………………………….
(Name and address of the Authority)
In accordance with the Energy (Electricity Supply and Installation Work) Regulations, 2022, I/We…………………………..……………………..……….………………………………….
(Name and address of Electrical Contractor) hereby give notice that I/we propose to carry out the following work as under:
for……………………………………………………….……………………………………...
(Name of consumer) of…………………………………………………………….…………………………………
(Address of consumer) at…………………………………………………………….…………………………………
(Situation of Property) of land office reference No…………………………………..………………………………..
Details of Installation:
Nature of work: new installation/addition/modification of an existing installation.
(Delete where not applicable)
Nature of installation (new, addition or modification) ……………………………………….....
Type of supply (Single or Three phase) …………………………………………………………
Supply voltage (Low, Medium or High) ………………………………………………………...
GPS coordinates of the premises ………………………………………………………………..
Connection Service Provider Ref. No. ………………………………………………………….
Proposed situation of meter-boards(s) in the case of a new installation or if the site of an existing board is to be changed will be
………………………………………………………
A service line is/is not required……………………………………………………………….
I/we have Electrical Contractors Licence No…………………………….…………………..
THE KENYA GAZETTE 6th December, 2024
Class……………………… valid for the current year
Date………………………………… …………………………………..…………………...
Signature of Electrical Contractor …………………………………………………………..
NOTE - Any person who submits a Certificate which is false in any material particular is liable to prosecution under the Energy Act of 2019 and the
Energy (Electricity Supply and Installation Work) Regulations of 2023.
FORM 005: CERTIFICATE OF COMPLETION
FOR CONSUMER INSTALLATIONS AND SPECIAL INSTALLATIONS
No……………………..
To:
…………………………………………………………………………………...………
(Name and address of electricity supplier)
In accordance with the Energy (Electricity Supply and Electrical Installations Work) Regulations, 2022, I/We …………………………..……………………………………………………...…………
(Name and address of Electrical Contractor)
Holding Licence No………………………class ……………………………, hereby give notice that the under-mentioned work in connection with the installation of the premises of:
Name……………………………………………………………………………………...…….
Address…………………….……………………………………………………………. is now completed and ready for testing and connection.
A service line is/is not required: ………………………………………………......
Details of Installation:
Nature of installation (new, addition or modification) ……………………………………….....
Type of supply (Single or Three phase) …………………………………………………………
Supply voltage (Low, Medium or High) ………………………………………………………...
GPS coordinates of the premises ………………………………………………………………..
Specific description of the Installation …………………………………...…...………………….
……………………………………………………………………………………………………
The work has been carried out, inspected and tested and is in compliance with the Energy (Electricity Supply and Electrical Installations Work)
Regulations, 2023 and applicable electrical installation standards.
The electrical test values are as follows:
No. Inspection/test Finding/value Remark
1 Inspection
2 Polarity tests
3 Continuity tests
4 Earth resistance test value
5 Insulation resistance test value
6 Other tests (specify)
(Add rows for any additional tests as appropriate)
Name of licensed electrical worker in charge……………………………….………..………….
Class of Licence held…………………. Licence No………………….…..……..………....
…………………………………………………………………………………..........……….…
I/We confirm that the test values are in compliance with KS 662-2018 and certify that the electrical installation is ready for energization.
Signatures of
Licensed electrical worker in charge …………………… Date………………………………
Electrical Contractor/Worker………………………….……………… Date…………………
(For office use by the electricity supplier)
Connection order No…………………………….
NOTE - Any person who submits a Certificate which is false in any material particular is liable to prosecution under the Energy Act of 2019 and the
Energy (Electricity Supply and Installation Work) Regulations of 2023.
FORM 006: CERTIFICATE OF COMPLETION
6th December, 2024 THE KENYA GAZETTE
FOR: ELECTRIC SUPPLY LINES
No……….………
DETAILS OF THE CLIENT/LICENSEE
.............................................................................................................................................................................................................................................
INSTALLATION ADDRESS
.............................................................................................................................................................................................................................................
DESCRIPTION AND EXTENT OF THE INSTALLATION
New Installation Description of Installation:
........................................................................................................................................................................
Addition to an existing installation
Description of Installation (Extent of installation covered by this Certificate):
........................................................................................................................................................................
Alteration to an existing installation
Description of Installation (Extent of installation covered by this Certificate):
........................................................................................................................................................................
FOR DESIGN WORK
I/We, being the person(s) responsible for the design of the electrical installation (as indicated by my/our signatures below), particulars of which are described above, having exercised reasonable skill and care when carrying out the design, hereby CERTIFY that the design work for which I/we have been responsible is to the best of my/our knowledge and belief in accordance with the Section 151 of the Energy Act of 2019, The Energy
(Electricity Supply and Installation Work) Regulations of 2023, electric supply lines design and construction standards, and the terms and conditions of Contract (insert Contract particulars) , except for the departures, if any, detailed as follows:
Details of departures:
.............................................................................................................................................................................................................................................
The extent of liability of the signatory or signatories is limited to the design work for the installation described above as the subject of this
Certificate.
Designer: Name ...............................................Signature: ..................................... Date: ...................
FOR CONSTRUCTION WORK
I, being the person responsible for the construction of the electrical installation (as indicated by my signature below), particulars of which are described above, having exercised reasonable skill and care when carrying out the construction hereby CERTIFY that the construction work for which I have been responsible is to the best of my knowledge and belief in accordance with Section 151 of the Energy Act of 2019, The Energy
(Electricity Supply and Installation Work) Regulations of 2023, electric supply lines design and construction standards, and the terms and conditions of Contract (insert Contract particulars) , except for the departures, if any, detailed as follows:
Details of departures:
.............................................................................................................................................................................................................................................
The extent of liability of the signatory or signatories is limited to the construction work for the installation described above as the subject of this
Certificate.
Constructor/Contractor: Name ..........................Signature: .......................... Date: ...................
FOR INSPECTION AND TESTING WORK
I, being the person responsible for the inspection & testing of the electrical installation (as indicated by my signature below), particulars of which are described above, having exercised reasonable skill and care when carrying out the inspection & testing hereby CERTIFY that the work for which I have been responsible is to the best of my knowledge and belief in accordance with Section 151 of the Energy Act of 2019, The Energy
(Electricity Supply and Installation Work) Regulations of 2023, electric supply lines design and construction standards, and the terms and conditions of Contract (insert Contract particulars) , except for the departures, if any, detailed as follows:
Details of departures:
.............................................................................................................................................................................................................................................
The extent of liability of the signatory or signatories is limited to the inspection and testing work for the installation described above as the subject of this Certificate
A detailed inspection and test report is attached.
Inspector/Contractor: Name ...................................Signature: ....................... Date: ...................
NOTE - Any person who submits a Certificate which is false in any material particular is liable to prosecution under the Energy Act of 2019 and the
Energy (Electricity Supply and Installation Work) Regulations of 2023.
TENTH SCHEDULE [r. 25(2)]
DEFECTIVE INSTALLATION NOTICE
<<Letter head of Connection Service Provider including address>>
RE: Defective Installation Notice
Date
Customer Name Meter No/Account No
THE KENYA GAZETTE 6th December, 2024
Supply Ref No Completion Certificate No
Location
Dear Customer
This is to advise that we called at your premises on the____day of 20____for the purposes of inspecting and testing:
Electrical installations Meters
Connection to additional loads Others (specify)
The following are findings from our visit:
Your supply installation was found to be defective in regard to:
i.
ii.
iii.
As a result:
Your power supply was disconnected in accordance with the terms governing your Electricity Supply Contract, and in accordance with the provision of Sub-section 151(3) of the Energy Act of 2019 and Regulation 24 and 25 of the Energy (Electricity Supply and
Installation Work) Regulations of 2023.
You are required to engage a licensed electrical contractor to regularize the issues identified and contact the undersigned to arrange for inspection and testing.
A check meter shall be installed, meter(s) replaced at your cost not less than 2 days from the date of this notice or on such earlier date as you may authorize.
For further information, please contact:
Name:
Telephone:
Physical Address:
Dated: Time:
Inspector's Name: S/No:
Designation:
Signature:
ELEVENTH SCHEDULE [ (r. 26(1), 26(2)]
PERIODIC INSPECTIONS AND TESTING OF INSTALLATIONS
Type of installation Maximum period between inspections and testing of installations
Domestic accommodation (General) 10 years
Domestic accommodations (Rented houses and flats) 5 years
Commercial premises Change of occupancy/5years
Educational establishments 5 years
Laboratories, Hospitals and Clinics 5 years
Industrial premises 3 years
Cinemas and Theatres 3 year
Churches, mosques, temples 5 years
Leisure complexes (excluding swimming pools) 3 year
Swimming pools 1 year
Places of public entertainment 3 year
Agricultural and horticultural 3 years
Caravans 3 years
Caravan parks/sites 1 year
Emergency lighting 3 years
Fire alarm systems 1 year
Launderettes and Laundry 1 year
6th December, 2024 THE KENYA GAZETTE
Petroleum service stations 1 year
Public Houses 5 years
Marinas 1 Year
Highway power supplies/ Street lights 2 years
Construction site/Temporary installation 3 months
Electric vehicle charging stations 1 year
Offices 5 years
Shops 5 years
Restaurants and hotels 5 years
Village halls/Community Centres 5 years
Fish farms 1 year
§ In this Schedule, “domestic premises” means premises used wholly or mainly for domestic purposes
§ Within two years of coming into force of these Regulations, all installations which are due for inspections shall be inspected and tested.
TWELFTH SCHEDULE, [r 27(4,i)]
FORM 007: PERIODIC INSPECTION AND TEST CERTIFICATE
A: DETAILS OF THE PERSON ORDERING THE INSPECTION AND TESTING
Name
Physical Address Postal Address
Telephone Email
B: DETAILS OF THE INSTALLATION
Occupier/Owner
Physical Address
Postal Address
Email Telephone
Type of Premises (Domestic, Commercial, Industrial, other.
Estimated age of wiring system (years)
Evidence of additions or alterations? (Yes/No) Installation records available? (Yes/No)
Date of last inspection Power Utility Account Number (as applicable)
C: EXTENT AND LIMITATIONS OF INSPECTION AND TESTING
Extent of the electrical installation covered by this certificate
Agreed limitations including the reasons(s)
It should be noted that cables concealed within trunking and conduits, under floors, in roof spaces, and generally within the fabric of the building or underground, have not been inspected unless specifically agreed between the client and inspector prior to the inspection. An inspection should be made within an accessible roof space housing other electrical equipment.
D: SUMMARY OF THE CONDITION OF THE INSTALLATION & RECOMMENDATIONS
General condition (Satisfactory/Unsatisfactory)
Identified Defects/Observations
Recommendations/Remedial Actions
Subject to the necessary remedial action being taken, I / We recommend that the installation is further inspected and tested by (insert date) for the following reasons (give the reasons)
E: DECLARATION
I/We, being the person(s) responsible for the inspection and testing of the electrical installation (as indicated by my/our signatures below), particulars of which are described above, having exercised reasonable skill and care when carrying out the inspection and testing, hereby declare that the information in this certificate provides an accurate assessment of the condition of the electrical installation taking into account the stated extent and limitations indicated section C.
Inspected and Tested by:
Name of Electrical Contractor (Inspector) .....................................................................................
Electrical Contractor Class Licence Class and Number ................................................................
Signature/Stamp ................................ Date ..........................................
The attached inspection and test report is part of this document and this certificate is valid only when they are attached to it.
THE KENYA GAZETTE 6th December, 2024
THIRTEENTH SCHEDULE [r.28 (1)]
PENALTIES FOR NON-COMPLIANCE
Regulation Default Penalty/Fine
23(2), 24(8) Interfering and/or tampering with a meter whilst in the premises of the consumer upon whose premises the meter was placed
A fine not exceeding fifty thousand shillings or to imprisonment for a term not exceeding two years or to both.
5(1) and 5(2) A person undertaking electrical installation work without being an electrical worker qualified for such work or not being under the supervision of a qualified electrical worker.
A fine not exceeding one hundred thousand shillings or to a term of imprisonment not exceeding six months or to both.
5(2) A consumer (owner or occupier) who permits a person who is not duly authorized as an electrical worker or contractor to carry out electrical installation work in his premises.
A fine not exceeding fifty thousand shillings or to a term of imprisonment not exceeding three months or to both
5(1) A Connection Service Provider who permits a person who is not duly authorized as an electrical worker or contractor to carry out electrical installation work on his behalf.
A fine not exceeding one million shillings or to a term of imprisonment not exceeding six months or to both.
Various Giving false or misleading information in relation to any electrical installation work;
A fine not exceeding ten million shillings or imprisonment for a term not exceeding five years, or both.
24(2), 24(3) Submits or causes to be submitted to any Connection Service
Provider or to the Authority a Commencement of Work Notice or Completion Certificate which he knows or has reason to believe contains false information;
A fine of fifty thousand shillings for each false completion certificate issued.
27(5) Submits or causes to be submitted to any Connection Service
Provider or power line operator a Completion Certificate which he knows or has reason to believe contains false information;
A fine of one million shillings for each false completion certificate issued.
24(3) Fails or willfully refuses to issue a completion certificate for completed electrical installation work.
A fine of one hundred thousand shillings.
27(5) Fails or willfully refuses to issue a completion certificate for completed electrical installation work for electric power line.
A fine of one million thousand shillings.
5(1) and 5(2) Undertakes or carries out by himself, his servant, or agent any electrical installation work at any time whilst his business is not licensed as an electrical contractor or while the licence of such business is suspended or revoked;
A fine not exceeding fifty thousand shillings or to a term of imprisonment not exceeding three months or to both
26 Fails or refuses to conduct periodic inspection and testing as set out under these Regulations
Disconnection of supply or closure of facility
DANIEL K. BARGORIA, MR/6485619 Director-General.
Dated the 6th December, 2024.
DANIEL K. BARGORIA,
Director-General.
Extracted Entities (1)
previous_gazette_ref
16247
Details
- Act / Legislation
- THE ENERGY ACT
- Reference
- No. 1 of 2019
- Section
- section 9
- Signed By
- DANIEL K. BARGORIA
- Title
- Director-General
- Date Signed
- 6th December 2024
- Page
- 38
- Extraction Method
- regex
Source Gazette
Vol. CXXVI No. 213
Published 1st July 2024