GAZETTE NOTICE NO. 15540
GAZETTE NOTICE NO. 15540
THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
(No. 8 of 1999)
ACT
PURSUANT to section 59 of the Environmental Management and
Coordination Act, 1999, the National Environment Management
Authority (NEMA) has received an Environmental Impact Assessment
Study Report for the above proposed project.
The proponent, Local Authorities Pension Trust Registered Trustees
(LAPTRUST), proposes to construct 30 No. floors office building comprising 2 No. basements (parking space and waste water treatment plant), ground floor (parking spaces and commercial spaces) and 1st and
2nd floor(parking spaces), 3rd and 4th floor(Conference Centre 1 and
Conference Centre 2). 5th to 28th floors comprising office units, 29th and 30th floor (2 No. restaurants, health club and observation desk), lifts, other associated amenities and facilities on plot L.R. No.
Nairobi/Block 1/383, along Argwings Kodhek Road, Hurligham, Nairobi City County.
The following are the anticipated impacts and proposed mitigation measures:
Impacts Mitigation Measures
Soil erosion • Install drainage structures to control flow of storm water.
• Ensure and management of excavation activities.
• Control earthworks.
Loss of vegetation • Only area earmarked for development should be cleared.
• Plant trees, shrubs and flowers on remaining open spaces.
Changes in hydrology/impended drainage/deep excavations
• Proper installation of drainage structures.
• Install cascades to break the impact of water flowing in the drains.
• Ensure efficiency of drainage structures through proper design and maintenance.
• Provide gratings to the drainage channels.
• A geotechnical survey shall be conducted and the recommendations thereof followed.
There shall be no blasting during excavation
• A methodology for excavation shall be generated as required by NCA.
Air pollution • Stockpiles of earth should be sprayed with water or covered during dry seasons.
• Provide dust masks for personnel in dusty areas.
• Sensitize construction workers on pollution control measures.
• Cover all trucks hauling soil, sand and other loose materials.
Noise pollution • Install suitable barriers to shield compressors and other small stationary equipment where necessary.
• Display signs to indicate construction activities.
• Maintain all equipment.
• Adhere to provisions of Noise
Prevention and Control Rules 2005, Legal Notice No. 24 regarding noise limits at the workplace as well as EMCA (Noise Excessive
Vibration Pollution Control
Regulations), 2000.
Impacts Mitigation Measures
Public health, occupational health and safety
• Train staff/workers on occupational health and safety.
• Provide full protective gear and workmen’s compensation cover in addition to the right tools and operational instructions and manuals during construction.
• Design of sewerage system should be as provided in the plans and should be constructed to approved size and design, standard and of approved materials.
• Ensure use of standard construction materials and to the specifications.
Avoid undesirable, substandard, hazardous or unauthorized materials during construction and maintenance.
• Sensitized staff on social/health issues such as drugs.
Road traffic disruption • No overloading of trucks and good driving practices to be practiced.
• Suitable junction/access point to be provided.
• Use of appropriate and legible signage.
• Employment of formal flagmen/ women to ensure the public safety.
• Follow the traffic management plan throughout the project cycle.
Insecurity • Provision of security guards, CCTV cameras, security lights and other security apparatus during the entire project cycle.
• Construction work timings shall only in line with the NEMA licensing conditions.
Increased water usage • An alternative water source shall be provided. The proponent shall drill a borehole at the proposed site.
• Management of water usage. Avoid unnecessary wastage.
• Recycling of water at the construction phase where possible.
• Make use of roof catchments to provide water i.e. for general purpose.
Increased waste generation
• Adopt waste minimization at source.
• Monitoring the fate of disposed wastes to ensure they are legally land filled at a recognized controlled site.
• Adhering to waste management regulations of 2006.
The full report of the proposed project is available for inspection during working hours at:
(a) Principal Secretary, Ministry of Environment, Climate
Change and Forestry, NHIF Building, 12th Floor, Ragati
Road, Upper Hill, P.O. Box 30126–00100, Nairobi.
(b) Director-General, NEMA, Popo Road, off Mombasa Road, P.O. Box 67839–00200, Nairobi.
(c) County Director of Environment, Nairobi City County.
22nd November, 2024 THE KENYA GAZETTE
A copy of the EIA report can be downloaded at www.nema.go.ke, The National Environment Management Authority invites members of the public to submit oral or written comments within thirty (30) days from the date of publication of this notice to the
Director-General, NEMA, to assist the Authority in the decision making process regarding this project.
Comments can also be e-mailed to dgnema@nema.go.ke
MAMO B. MAMO, Director-General, MR/6475192 National Environment Management Authority.
Dated the 22nd November, 2024.
MAMO B. MAMO,
Director-General, National Environment Management Authority.
Extracted Entities (1)
previous_gazette_ref
15540
Details
- Act / Legislation
- THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
- Reference
- No. 8 of 1999
- Section
- section 59
- Signed By
- MAMO B. MAMO
- Title
- Director-General, National Environment Management Authority
- Ministry
- Ministry of Environment, Climate
- Date Signed
- 22nd November 2024
- Page
- 63
- Extraction Method
- regex
Source Gazette
Vol. CXXVI No. 203
Published 6th March 2024