GAZETTE NOTICE NO. 10505
GAZETTE NOTICE NO. 10505
THE WATER ACT
(No. 43 of 2016)
EXTENSION
in accordance to the requirements of section 139 of the Water Act, 2016.
After considering the application, the written and oral submissions by all stakeholders during the consultation period, and based on latest available data, WASREB has determined an upward tariff review for EWASCO is justified in order to improve service delivery, operate sustainably and protect consumer interests by meeting the tariff conditions Attached to the tariff.
WASREB gives a one (1) month's notice to all existing and potential customers of EWASCO that the approved tariffs for the four financial years, 2019/20, 2020/21, 2021/22 and 2022/23 shall be as follows:
1.0 Approved Tariff Structure
1.1 Water Tariff Structure for the period 2019/20, 2020/21, 2021/22 and 2022/23
Customer Category Approved Tariff Structure
Consumption Block in M3 KSh.
Domestic
1-6 45
7-20 60
21-50 70
51-100 80
101-300 95
Customer Category Approved Tariff Structure
Consumption Block in M3 KSh.
>300 130
Multi-Dwellin • Units (>5 units with a shared connection) Per M3 60
Commercial/ Industrial and Government
1-50 70
51-100 80
101-300 95
> 300 130
Public Schools, Universities and colleges
1-600 50
601-1200 60
>1200 90
Standpipes/Kiosks Per M3 35
1.2 Indexation of the Approved Tariff
The utility's tariff shall be eligible for annual indexation of the approved tariff, as per the regulations of the Water Services Regulatory Board
(WASREB). The inflation adjustment shall come into effect every July of the tariff period commencing July 2021.
1.3 Sewerage Tariff
(a) Consumers with a Water Connection
Sewerage volumes for customers with a water connection shall be determined at 75% of the volume of water consumed at the tariff of water specified in 1.1 above.
(b) Consumers without a Water Connection
Sewerage consumers without a water connection shall be charged as follows:
• Domestic (Single dwelling unit): Ksh. 300 per month.
• All other categories: 75% of the volume of water consumed, as per the metered source, at the rates specified in 1.1 above.
2.0 Miscellaneous Charges
Bend Service Charge (KSh.)
Standing Charge Per Connection per Month
Connection Size
1/2 inches 50
'A inches 100
1 inch 250
1 1/2 inches 250
2 inches 250
3 inches 450
4 inches 800
6 inches 1250
8 and above 2000
Water Deposit
Category of consumer
Domestic 2500
Retail shops less than 10 m3 3000
Retail shops more than 10 m3 3,500
Bar, restaurants less than 15 m3 4000
Bar, restaurants more than 15 m3 6,000
Hotel class "A" and-"B" less than 150 m3 12,000
Hotel class "A" and "B" more than 150 m3 15000
Hotel class "C" and 'D' less than 150 m3 • 18000
Hotel class "C" and 'D' more than 150 m3 20,000
Hospitals more than 150 m3 20,000
Health centres less than 150 m3 12,000
Schools and other institutions more than 200 m3 20,000
Schools less than 200 m3 10,000
Minor construction sites more than 200 m3 15,000
Major construction sites more than 300 m3 50,000
Light industries less than 200 m3 30,000
Medium industrial between 200 m3 and300 m3 50,000
Heavy industries more than 300 m3 100,000
Water Kiosks 5,000
Customers with only sewer connection to be charged a deposit equivalent to water connection
Other Charges
Service
New water connection fee — Connection size: 1/2 inch to 1 inch 2,500
New water connection fee — Connection size: 1.5 inches to 3 inches 7,500
New water connection fee — Connection size above 3inches 15,000
Water Reconnection fee — at meter point 1,000
Water Reconnection fee — at mains 5,000 and double deposit
8th November, 2019
Iteml Service Charge (KSh.)
Tanker — 8000, 16,000 litres 2,500, 5,000 respectively per tanker within EWASCO area for all consumers
Sale of water per m3 at bowling point (own tanker) 80
Replacement of stolen or damaged meters 100% of the market cost of the meter
Meter testing on request 500
Sewer Connection- Residential/ Domestic 5,000
Sewer Connection- Commercial, Government, schools, Universities and Colleges
7,500
Sewer Connection- Industrial 15,000
Private sewer unblocking 2,500
Leak detection services 1,000
Sewer Reconnection fee 15,000
Statement of account fees 200
For cutting off the supply at the request of the consumer 200
For turning on the supply otherwise than in respect of a first connection 200
Exhauster Services (Company Exhauster) 5,000 for other customers and 4,000 for informal settlements
Private Exhausters (Dumping into the company's sewer system) 15,000per Truck per month
Penalties
Illegal water connection, —Commercial, Industry, Construction (Fraud) 100,000 plus estimated consumption during the period of the illegality
Illegal water connection, (Fraud) — Domestic 30,000 plus estimated consumption during the period of the illegality
Overcharging (fraud) at water kiosk 15,000
Illegal sewer connection—Commercial, Industry, Construction 100,000
Illegal sewer connection—Domestic, Government, Schools, Universities and Colleges
30,000
Self-reconnection after cut off for non-payment 5,000 and billing to be backdated from date of cut off
Surcharge for tampering with meters (this to include meter removal, reversing of meter etc)
5,000
Surcharge for direct suction of water from the supply line using a pump 10,000
3.0 Approved Cost Structure
Below is the summary of the cost structure that makes up the Average annual total costs to be incurred by EWASCO during the tariff period.
KSh. KSh.
A. Cost Subject to Annual Indexation
Operations and Maintenance costs 263,090,314
B. Fixed Costs
Average Annual Investment Cost 52,643,687
Average Annual Debt Repayment 43,959,971
Average Annual Asset Renewal 60,925,553
Sub-total—Fixed Costs 157,529,211
Total Average Annual Cost 420,619,525
Projected Average Annual Revenue 501,952,566
Average Annual Cost Coverage 119%
4.0 Conditions attached to the Tariff Approval
The tariff adjustment approval is approved for four years and during which all the assumptions made in the tariff projections will be monitored.
The conditions attached to this approval which shall form part of the license conditions of Embu Water and Sanitation Company are:
•
(i) Service Delivery Conditions attached to the Tariff
Target 2019/20 2020/2021 2021122 2022/23
Water Coverage (%) 94 96 97 98
Sewerage Coverage (%) 23 -25 27 29
Water quality standards (%) 1009 compliance with the quality standards
Non-Revenue Water (%) 36% 33% 30% 27%
Hours of Supply (Hrs) 24 24 24 24
Staff per 1000 connections 4 4 4 4
Metering ratio (%) 100 100 100 97
Collection Efficiency (%) 92% 94% 95% 95%
Resale at Kiosk Regulate resale by kiosk vendors at KSh. 2 per 20-litres. Tariffs at kiosks must be displayed at strategic points for public awareness
(ii) Annual budgets: The utility shall adhere to the budgetary levels set in the tariff.
(iii) Surpluses: The surpluses projected to be realized shall only be used on the rehabilitation/replacement of dilapidated water networks, in order to curb physical losses of water. EWASCO shall in the first year of tariff implementation identify priority networks to be replaced/ rehabilitated and communicate the same to WASREB in writing.
(iv) Catchment Protection: The utility shall undertake measures to conserve/protect the catchment areas of their source of water as part of
Corporate Social Responsibility.
(v) Reporting: The utility shall submit to WASREB a quarterly performance report in the format provided.
(vi) Investments: The utility shall undertake the following investments below during the tariff period and also submit quarterly progress reports on the same.
INVESTMENTS BY EMBU WATER AND SANITATION COMPANY FOR THE TARIFF PERIOD 2019/2020
Project Area Guide Size Sample Descriptions Unit Quantity
Project Cost
(KSh.)
A. Purchase and
Installation of
Regional Master meters
•
North West Zonal Meters DN 90 Mechanical Cold-Water meter
Woltmann Water meter
No. 4 95,600
Zonal Meters DN 100 Mechanical Cold-Water meter
Woltmann Water meter
No. 2 65,000
Zonal Meters DN 150 Automatic Meter Reading
(AMR) Meter type
No. 2 190,000
Zonal Meters DN 200 Automatic Meter Reading
(AMR) Meter type
No. 1 145,000
North East Zonal meters DN 90 Mechanical Cold-Water meter
Woltmann Water meter
No. 2 47,800
Zonal meters DN 100 Mechanical Cold-Water meter
Woltmann Water meter
No. 2 65,000
Zonal meters DN 150 Automatic Meter Reading
(AMR) Meter type
No. 2 190,000
Zonal meters DN 200 Automatic Meter Reading
(AMR) Meter type
No. 1 145,000
South West Zonal Meters DN 90 Mechanical Cold-Water meter
Woltmann Water meter
No. 2 47,800
Zonal Meters DN 100 Mechanical Cold-Water meter
Woltmann Water meter
No. 2 65,000
Zonal Meters DN 150 Automatic Meter Reading
(AMR) Meter type
No. 4 380,000
Zonal Meters DN 200 Automatic Meter Reading
(AMR) Meter type
No. 3 435,000
South East Zonal Meters DN 90 Mechanical Cold-Water meter
Woltmann Water meter
No. 3 71,700
Zonal Meters DN 100 Mechanical Cold-Water meter
Woltmann Water meter
No. 2 65,000
Zonal Meters DN 150 Automatic Meter Reading
(AMR) Meter type
No. 2 190,000
Zonal Meters DN 200 Automatii Meter Reading
(AMR) Meter type
No. 1 145,000
Kanamori Zonal meters DN 90 Mechanical Cold-Water meter
Woltmann Water meter
No. 2 47,800
Zonal meters DN 100 Mechanical Cold-Water meter
Woltmann Water meter
No. 2 65,000
Zonal meters DN 150 Automatic Meter Reading
(AMR) Meter type
No. 1 95,000
Sub-total 40 2,550,700
B. Purchase of
Movable Assets
Procurement of computers, software and
Accessories
ICT support Computer Server Lumpsum 1 2,000,000
Computers and Accessories Lumpsum 2,715,000
Sub-total 4,715,000
B. Purchase of
Movable Assets
Motor vehicles and motor cycles
Motor cycles 125 cc Stroke 54, Engine
Displacement 123, Max Power
10.7 bhp@7500 rpm
No. 5 1,000,000
Motor vehicle 3000 cc Diesel; 5 speed Manual;
transfer box for 4 x 4 select
No. 1 6,000,000
Sub-total 6 7,000,000
C. Extension of
Service Lines
Extension of service lines-
New Distribution
Area
Kithimu Distribution
Area
DN 50 50 mm diameter PN 16 HDPE pipe
_ Metres 3550 745,500
DN 63 63 mm diameter PN 16 HDPE i pipe
Metres 4,000 1,220,000
Ena Market
Distribution Lines
DN 50 50 mm diameter PN 16 HDPE pipe
Metres 2,300 483,000
Ugweri Market
Distribution Lines
DN 50 50 mm diameter PN 16 HDPE pipe
Metres 2,250 472,500
DN 63 63 mm diameter PN 16 HDPE pipe
Metres 3,500 1,067,500
Karurumo Market
Distribution Lines
DN 50 50 mm diameter PN 16 HDPE pipe
Metres 1,500 315,000
DN 63 63 mm diameter PN 16 HDPE pipe
Metres 2,500 762,500
Sub-total 25,100 5,066,000
D. NRW Reduction
Plan
Reduce NRW Planned activities to reduce NRW(Phasel) 10,050,000
8th November, 2019
Project Area Guide Size Sample Descriptions Unit Quantity
Project Cost
(KSh.)
Total
33,381,700
INVESTMENTS BY EMBU WATER AND SANITATION COMPANY FOR THE TARIFF PERIOD 2020/2021
Project Area Guide Size Sample Descriptions Unit Quantity
Project
Cost (KSh.)
A. Purchase of
Movable Assets
Motor vehicles and motor cycles Motor cycles
125 cc Stroke 54, Engine Displacement 123, Max Power 10.7 bhp@7500 rpm
No.
10 2,000,000
Accounting Software Upgrade 6,000,000
Motor vehicle
Procurement of Motor Vehicle
(Sampling Vehicle)
No.
1 6,000,000
Sub-total 14,000,000
C. Sewer
Improvement
Phase 2 -Blue valley
Estate
Construction of Manholes No.
150 5,250,000
Laying of sewer pipes Metres 4,000 28,000,000
Sub-total 4,150 33,250,000
D. Rehabilitation of
Service Lines
Water System rehabilitation
Kaunda Estate
Rehabilitation
DN 110 110 mm diameter PN 16 HDPE pipe Metres
2,700 2,384,100
Muchonoke—Minuri— -
Mbita
DN 160 160 mm diameter PN16 UPVC pipe (6M
UPVC Straights)
Length
4,500 5,226,000
Sub-total 7,200 7,610,100
E. Extension of
Service Lines
Implemented internally by
Kithimu Distribution
Area Neighbourhood
'DN 50 50 mm diameter PN 16 HDPE pipe Metres
6,000 1,260p00
WSP DN 63 63 mm diameter PN 16 HDPE pipe Metres 5,000 1,525,000
Ena Market
Distribution Lines
Neighbourhood
DN 50 50 mm diameter PN 16 HDPE pipe Metres
2,500 525,000
Ugweri Market
Distribution Lines
Neighbourhood
DN 50 50 mm diameter PN 16 HDPE pipe Metres
2,500 525,000
DN 63 63 min diameter PN 16 HDPE pipe Metres 5,000 1,525,000
Karururno Market
Distribution Lines
DN 50
Neighbourhood
50 mm diameter PN 16 HDPE pipe Metres
2,500 525,000
DN 63 63 nun diameter PN 16 HDPE pipe Metres 3,000 915,000
Gachoka—Gachuriri
Area
DN225 225 mm diameter PN16 (6M UPVCMetres
Straights) 5,500 12,969,000
Sub-total
•
19,769,000
F. NRW Reduction
Plan
Reduce NRW Planned activities to reduce
—
NRW (Phase 2)
12 400 000
Total 53,779,100
INVESTMENTS BY EMBU WATER AND SANITATION COMPANY FOR THE TARIFF PERIOD 2021/2022
Project Area ' Guide Size Sample Descriptions Unit' Quantity Project Cost (KSh.)
A. Purchase and
Installation of
Regional
Master meters
All 0.5" replacements, new connections and conversion from flat rat
No. 4,000 14,000,000
0.75" No. 150 600,000
1" No. 75 637,500
1.5" No. 75 1,650,000
• 2" No. 50 1,775,000
3" No. 50 2,100,000
4" No. 50 2,500,000
6" No. 25 2,375,000
8" No. 5 725,000
10" No. 5 1 ,250 ,000
12" No. 5 1,500,000
Sub-total 4,490 29,112,500
B. Purchase of
Movable Assets
Motor cycle Procurement of
Motorbikes-125 cc
, No. 10 2,000,000
Motor vehicles
"
Procurement of Motor
Vehicle-3000 cc
No. 1 6,000,000
Sub-total 11 8,000,000
C. NRW
Reduction Plan
Reduce NRW Planned activities to reduce NRW (Phase 3)
12,100,000
Rehabilitation of Service Lines
Improvement of P.I line
DN 160 160 mm diameter
PN16 (6M UPVC
Straights)
Metres 3,750 4,355,000
Kanyariri—Muchonoke—
Cianyi—Kavindi (old line)
DN 160 -160 mm diameter
PN16 UPVC pipe (6M
UPVC Straights)
Length 5,000 5,806,667
Extension of service lines
Gachuriri—Makima DN225 225 mm diameter
PN16 (6M UPVC
Straights)
Metres 7,000 16,506,000
15,750 26,667,667
B. Improvement on treatment plant.
Extension of Karigiri
Treatment plant
Flocculation and
Sedimentation Tanks
Lumpsum 40,000,000
Sub-total 40,000,000
Total 120,235,167
2022-2023
Project Area Guide Size Sample Descriptions Unit
Project Cost
(KSh.)
A. Extension of service lines
New distribution area
Implemented internally by WSP
DN 75 Kithimu Distribution Lines Lumpsum 7,934,495
DN 75
Ena Market Distribution Lines—
Neighbourhood
Lumpsum
3,267,145
DN 160
Ugweri Market Distribution
Lines-Neighbourhood
Lumpsum
2,333,675
DN 160
Karurumo Market Distribution
Lines-Neighbourhood
Lumpsum
2,333,675
Contracted out Gachoka—Gachuriri—Makima N/A
50,080,245
65,949,235
B. Capital Works Office
Improvement
New office block Lumpsum
4,000,000
C. NRW Reduction
Plan
Reduce NRW Planned activities to reduce NRW (Phase 4)
12,000,000
Total 81,949,235
Dated the 24th October, 2019.
ROBERT GAKUBIA, Chief Executive Officer, MR/0449715
Water Services Regulatory Board.
Dated the 24th October, 2019.
ROBERT GAKUBIA,
Chief Executive Officer, Water Services Regulatory Board.
Extracted Entities (1)
previous_gazette_ref
10505
Details
- Act / Legislation
- THE WATER ACT
- Reference
- No. 43 of 2016
- Section
- section 72 (1) (b)
- Signed By
- ROBERT GAKUBIA
- Title
- Chief Executive Officer, Water Services Regulatory Board
- Date Signed
- 24th October 2019
- Page
- 33
- Extraction Method
- regex
Source Gazette
Vol. CXXI No. 152
Published 1st April 2019