GAZETTE NOTICE NO. 10528
GAZETTE NOTICE NO. 10528
THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
(No. 8 of 1999)
REGULATION
Pursuant to Regulation 21 of the Environmental Management and
Co-ordination (Impact Assessment and Audit) Regulations, 2003, the
National Environment Management Authority (NEMA) has received an Environmental Impact Assessment Study Report for the above proposed project
The proponent, Rareh Icon Solar Limited, is proposing to evacuate
132kV power from the solar PV plant to the Kiboko substation where it will be connected to the national grid. The main components of high-voltage electricity transmission line and associated facilities include; transmission pylons, transmission lines, access roads and substation. This project will be carried out in Makueni County.
The following are the anticipated impacts and proposed mitigation measures:
Impacts
Proposed Mitigation Measures
Air pollution
• Maintain vehicle and equipment according to manufactures' specifications.
• Use standard fuel and lubricants.
• Sprinkle water to work areas to reduce and prevent dust during dry weather periods.
• Clean access routes in surrounding area on a daily basis to prevent dust.
• Collect and hold sanitary and cleaning wastes in appropriate container.
• Workers who may unavoidably have to work in dusty workplaces should be provided with nose and ear masks to protect them from excessive dust.
Noise pollution
• Minimize noise according to NEMA, Kenya standards and World Bank guidelines.
• Control noise and vibration on site.
• Install adequate noise prevention devices, e.g.
mufflers on noise generating sources.
• Switch off engines of vehicles and machinery while not in use.
• Provide information to the local communities
(e.g. through the local system or local radio
(FM) stations) with regard to work programme, and strict adherence to such.
• Workers who may unavoidably have to work with noise generating equipment, e.g.
earthmoving equipment should be provided with ear plugs and advised/monitored to put them on.
8th November, 2019 THE KENYA GAZETTE 4451
Impacts Proposed Mitigation Measures
• Contain solid wastes so that no solid waste, fuels or oils should not be discharged into surface water bodies.
Proposed Mitigation Measures
• Confine access to restricted work sites.
.0 Undertaking training and capacity building for all workers on use of chemicals.
Impacts
Water pollution
Soil erosion and contamination
Solid waste generation
Impacts on flora and fauna
• Hold and store sanitary and cleaning wastes in appropriate containers to be disposed of at approved sites.
• Park vehicles preferably on paved platforms.
• Fuel storages should not leak, and should be periodically monitored, and repaired or replaced when necessary.
• Sites for cleaning, fuelling and maintaining vehicles should be able to prevent leakage
(e.g. paved).
• Maintain fuel and clean vehicles and equipment at workshops/sites with adequate leakage prevention (e.g. impermeable surface, settlers and oil separator).
• Carry out work under mild weather (not strong rains or winds);
• Remove and store topsoil in separate piles and reinstate after refilling of trenches, to enable natural revegetation.
• Storing all hazardous, sanitary and cleaning wastes in facilities approved by NEMA.
• Installing leak-proof fuel storages on concrete platform with gutters and grease separators, which are monitored periodically and repaired or replaced when required.
• Strictly enforce and monitor standard procedures for storing and handling hazardous wastes and raw material (e.g. fuel or chemicals).
• Place drums for oil storage on impermeable floors in the stores.
• Parking vehicles on paved platforms whenever possible.
• Treat wastewater from maintenance workshops in oil separators before discharge.
• The contractor should prepare a Solid Waste
Management Plan, as described in this report.
• The contractor should maintain records of types, quantities, origin, (temporary) storage, transport and elimination/reuse of solid waste.
• Any waste including excess soil should be disposed of at gazetted sites.
• Excavated soils should be reused as much as possible as filling material.
• Use licensed recycling companies to externally collect and recycle, recover or dispose off waste.
• Zone out working areas to reduce ecological destruction.
• Agree with and compensate owners of trees.
• Restore disturbed natural sites through environmental rehabilitation; restoring top soils and (re-)introduce genetic species similar to those destroyed.
Occupational • Ensure that work sites (especially excavation health and works), have proper protection with clear safety exposure marking of safety borders and signals and fence off all dangerous areas.
• Inform riparian neighbours about the construction programme in advance.
• Provide PPE to all workers using chemicals.
Increased • Inform local communities about the vehicular traffic construction programme in advance.
• Use reflective signature to direct traffic to designated areas.
• Use flag men to give directions to traffic.
• Install speed reduction humps at crossings of many people.
Spread of • Sensitize workers and the surrounding communicable communities on awareness, prevention and diseases and management of HIV/AIDS.
HIV/AIDS infection
• Provide information, education and communication about safe uses of drinking water.
• Provide an onsite clinic to provide Voluntary
Counseling and Testing (VCT) services to construction crew and provision of
Antiretroviral (ARVs) for vulnerable community members.
• Integrate monitoring of HIV/AIDS preventive activities as part of the construction supervision.
• Conduction of campaign meetings on transmission of diseases like HIV/AIDS and other STDs.
Raw material use • Consider environmental performance of suppliers of raw material in the selection process.
• Explore ways of reducing raw material use.
• Special emphasis should be made on raw materials that may be reused and/or recycled/recovered.
Gender-based • Effective and on-going community violence at the engagement and consultation, particularly community with women and girls.
level
• Review of specific project components that are known to heighten GBV risk at the community level, e.g. compensation schemes for women, employments schemes for women etc.
• Specific plan for mitigating these known risks, e.g. sensitization around gender-equitable approaches to compensation and employment.
Disturbance and • Provide temporary access ways with the interruption of approval of local authorities where access commercial and roads are closed.
social activities
• Reduce obstruction of access to and use and occupation of roads, footpaths and bridges.
• Protect any items and/or sites of archaeological or cultural value (e.g. private graveyards) discovered during works with the aid of the appropriate Authorities.
The full report of the proposed project is available for inspection during working hours at:
(a) Principal Secretary, Ministry of Environment and Forestry, NHIF Building, Community, P.O. Box 30126-00100, Nairobi.
(b) Director-General, NEMA, Popo Road, off Mombasa Road, '
P.O. Box 67839-00200, Nairobi.
Proposed Mitigation Measures
• Procure quantities of construction materials in line with the Bill of Quantities.
• Recycle as far as practical to curtail wastage.
• Source materials from sites which are compliant with EMCA Act, Cap. 387.
• Rehabilitate the existing boreholes and obtain water abstraction permits from WRA.
• Expand the existing water pan to increase capacity to harness runoff to supplement water supply from the boreholes.
• Replant trees in the section of the property that will not be developed.
• Compact loose soils and pave open areas of the plant.
• Retain vegetation cover in areas of the property that will not be developed.
• Register site as a workplace with DOSHS.
• Obtain insurance cover for workers.
• Provide adequate and appropriate PPE and enforce their use to both workers and visitors.
Proposed Mitigation Measures
• Provide employees with correct tools and equipment for the jobs assigned and train on their use.
• Ensure moving parts of machines and sharp surfaces are securely protected with guards.
• Provide first aid services and an emergency vehicle at the site.
• Regulate the entry of visitors to the site by deploying adequate security measures.
• Ensure proper storage and management of flammable materials within the project site, • Prepare and implement a fire and emergency response plan for the construction site.
• Comply with the provisions of OSHA, 2007.
• Install dust screens around the project site during construction, • Sprinkle water at the excavation areas and
Recess road.
• Use of enclosures, covers or stabilize construction materials storage piles, • Install signage and bumps along the access road to restrict speed limit, • Use low sulphur fuels to power vehicles and site Machinery, • Use of serviceable machinery/equipment and trucks, • Retain vegetation cover in areas of the property that will not be developed.
• Prkure and enforce the use of dust masks to workers and visitors to the project site, • Monitor fugitive MISSION:
• Comply with Environmental Management and
Co=ordination (Air Quality) Regulations, 2014.
• Delivery of raw materials, excavation and construction work will be limited to daytime hours.
• Provide and enforce the use of earmuffs to staff and visitors.
• Sensitize truck drivers to avoid unnecessary hooting and running of vehicle engines.
• Comply with Environmental Management and
Co-ordination (Noise and Excessive Vibration
Pollution) (Control) Regulations, 2009.
• Procure and deliver to the site mobile toilets from a NEMA licensed waste contractor.
• Comply with Environmental Management and
Co-ordination (Water Quality) Regulations, 2006.
• Procure and strategically place adequate solid waste collection bins with a capacity for segregation.
• Procure a sizeable central solid waste collection bin with chambers to accommodate separated waste.
• Create awareness on best waste management practices among the workers.
• Procure the service of NEMA licensed solid waste handler.
• Comply with Environmental Management and
Co-ordination (Waste Management)
Regulations, 2006.
(c) County Director of Environment, Makueni County, The National Environment Management Authority invites members of the public to submit oral or written comments within thirty (30) days from the date of publication of this notice to the
Director•General, NEMA, to assist the Authority in the decision making process of the plan.
MAMO B. MAMO, Ag. Director•©eneral, MR/0424989
National Environment Management Authority.
ClAzkrm NOTICE No. 10529
THE ENVIRONMENTAL MANAGEMENT AND
CO-ORDINATION ACT
(No. 8 of 1999)
THE NATIONAL ENVIRONMENT MANAGEMENT AUTHORITY
NOTICE TO THE PUBLIC TO SUBMIT COMMENTS ON AN
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT
FOR THE PROPOSED GALVANIZED ROOFING SHEETS PLANT
AND AUXILIARY FACILITIES IN LUKENYA AREA, MACHAKOS COUNTY
INVITATION OP PUBLIC COMMENTS
Pursuant to Regulation 21 of the'Environmental Management and
Co-ordination (Impact Assessment and Audit) Regulations, 2003, the
National Environment Management Authority (NEMA) has received an Environmental Impact Assessment Study Report for the above proposed project
The proponent, Maisha Mabati Mills Limited, is proposing to set up a galvanized roofing sheets plant and auxiliary facilities comprising installations of components such as; nitrogen and hydrogen generator, DO set, steam boiler plant, LPG storage tanks, water complex, capacitor bank, compressor, effluent water treatment plant, &mineralizing water treatment plant, drinking water treatment plant, effluent treatment plant, picking plant 9litie), acid regeneration plant
(ARP), cold rolling Mill, AMIN line, colour coating line, power station, laboratory, 2 administration buildings, parking area, 1-12N2 yard, access gates, overhead water tank, mill E14, 2 dispatch loading points, 4 Wegh bridges, auxiliary bay, workshop, roll grinder shop, pickled coil storage, cold rolled coil storage, CR slitter, furnace ECR, zinc and dross storage yard, hot rolled coil storage, pipe rain water drain, 2 gates on plot L.R. No. 12648/3 within Lukenya area, Machakos County.
The following are the anticipated impacts and proposed mitigation measures:
Impacts
Use of environmental resources
Environmental degradation
Occupational safety and health
Imparts
Air pollution
Noise pollution
Effluent generation and management
Solid waste generation and management
8th November, 2019 THE KENYA GAZETTE 4453
Impacts Proposed Mitigation Measures
Fuel, oil and • Prevent oil/grease spillages by employing grease skilled mechanics and sensitization.
management
• Procure and train workers on the use of oil spill containment kits.
• Pave the repairs and maintenance workshop with imperveous materials.
• Fit the repairs and maintenance area with oil and grease interceptors.
• Contract a NEMA licensed waste oil handler to manage the waste oil from the construction site.
Increased traffic • Expand the access road to the site to accommodate HCVs.
• Prepare a traffic management plan.
• Provide for proper deceleration and acceleration lanes for vehicles delivering raw materials.
• Provide sufficient parking for HCVs and machinery at the site.
• Offload construction materials on site.
• Erect proper signage and warnings on the access route to forewarn other road users on the use of the road by HCVs.
• Observe speed limits.
• Comply-with the Traffic Act, 2016.
The full report of the proposed project is available for inspection during working hours at
(c) Principal Secretary, Ministry of Environment and Forestry, NHIF Building, Community, P.O. Box 30126-00100, Nairobi.
(d) Director-General, NEMA, Popo Road, off Mombasa Road, P.O. Box 67839,00200, Nairobi.
(c) County Director of Environment, Machakos County.
The National Environment Management Authority invites members of the public to submit oral or written comments within thirty (30) days from the date of publication of this notice to the
Director-General, NEMA, to assist the Authority in the decision making process of the plan.
MAMO B. MAMO, Ag. Director-General, MR/0431527
National Environment Management Authority.
Dated the 8th November, 2019.
MAMO B. MAMO,
Ag. Director-General, National Environment Management Authority.
Extracted Entities (1)
previous_gazette_ref
10528
Details
- Act / Legislation
- THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
- Reference
- No. 8 of 1999
- Signed By
- MAMO B. MAMO
- Title
- Ag. Director-General, National Environment Management Authority
- Ministry
- Ministry of Environment And Forestry
- Date Signed
- 8th November 2019
- Page
- 54
- Extraction Method
- regex
Source Gazette
Vol. CXXI No. 152
Published 1st April 2019