GAZETTE NOTICE NO. 492
PURSUANT to clause 3 of Part III of the Schedule of Tariffs 2013, notice is given that all prices for electrical energy specified in Part II of the said Schedule will be liable to an inflation adjustment of plus 36 cents per kWh for all meter readings taken in Jan—June 2017.
Information used to calculate the adjustment:
INFAKenGen INFAKPLC INFAIPPs Last half-year Period Total
Inflation Costs Under/(Over)
Recovery
Escalated Cost 432,623,239.86 296,331,788.37 779,611,538.33 61,621,861.89 1,570,188,428.45
Total projected units generated or purchased by the Company in Jan —June 2016 (Gp) = 5,149,094,704 kWh
JOSEPH NG'ANG'A, MR/2484378
Director-General.
Extracted Entities (1)
previous_gazette_ref
492
Details
- Signed By
- JOSEPH NG'ANG'A
- Title
- Director-General
- Page
- 23
- Extraction Method
- regex
Source Gazette
Vol. CXIX No. 9
Published 5th January 2017