GAZETTE NOTICE NO. 10687
GAZETTE NOTICE NO. 10687
THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
(No. 8 of 1999)
REGULATION
Pursuant to Regulation 21 of the Environmental Management and
Co-ordination (Impact Assessment and Audit) Regulations, 2003, the
National Environment Management Authority (NEMA) has received an Environmental Impact Assessment Study Report for the above proposed project.
The proponent, Moi Teaching and Referral Hospital, is proposing to construct a new 4000 beds Multi-specialty Teaching and Referral
Hospital in Kiplombe, comprising an emergency area, 22No. general outpatient clinics on three floors, pediatric clinic areas, a five floor medical technology block comprising 15No. units, 6No. ward buildings with 36No. nursing units, administration office block, staff apartments, research development and innovation building, associated facilities and amenities.
The following are the anticipated impacts and proposed mitigation measures.
Impacts
Proposed Mitigation Measures
Vegetation
• Restore cleared sites with indigenous vegetation disturbance upon completion of construction.
• Levelling and grading of the resultant construction site.
Dust and exhaust • Provide workers with noise safety equipment emissions such as ear muffs.
• Conduction of regular air pollution/quality monitoring tests to ensure that the atmospheric air is not polluted by project activities.
• Sprinkle water on open grounds to minimize dust emissions.
19th October, 2018 THE KENYA GAZETTE 3629
Impacts Proposed Mitigation Measures
• Use of water sprays to arrest dust.
Noise and • For mobile equipment, fit efficient silencers and excessive enclose engine compartments in plant vehicles.
vibration
• For fixed plants, isolate source by enclosure in acoustic structure.
Impacts Proposed Mitigation Measures
Workers accidents • Workers to put on PPEs.
and hazards
• Conduct statutory trainings under the OSHA, 2007 Regulations.
• Provision of firefighting equipment in strategic and well labeled sites.
Increased safety and health risks
Squatters
Airborne emissions
Soil and water pollution
• Raise barriers around noisy equipment.
• Notify the public of construction activities that may be perceived as noisy and intrusive prior to starting construction.
• Ensure that noise and excessive vibration are within permissible levels as per the provision of the Environmental Management and
Coordination (Noise and Excessive Vibration
Pollution) (Control) Regulations, 2009.
• Use signage to warn staff and/ or visitors that are not involved in construction activities of areas that pose risk.
• Regular Supervision of workers to ensure that safety conditions are met.
• Develop evacuation procedures to handle emergency situations.
• Clear marking of work site hazards and training in recognition of hazard symbols.
• Containment of hazardous materials.
• Provide adequate protective gear to construction workers.
• Squatters to be meaningfully consulted and given enough notice prior to eviction/relocation.
• Eviction/relocations to be done in a humane manner.
• Support squatters to restore their livelihoods.
• Regular servicing to maintain efficiency.
• Ensure no burning of waste on sites/non- designated areas.
• Covering open stockpiles of construction materials during rainy season.
• Implementation of erosion and sediment control measures such as silt fences.
• Control the earthworks.
• Landscaping to create contours towards the drainage systems.
• Create embankments around the premises with excavated earth to prevent loss.
• Reinstatement to ensure that backfill material is compacted to a similar value to the surrounding soils.
• Seeding and planting of trees, shrubs and ground cover for temporary or permanent stabilization of soil.
• Conduct drills at reasonable intervals to test the disaster preparedness level.
The full report of the proposed project is available for inspection during working hours at:
(a) Director-Generul, NEMA, Popo Road, off Mombasa Road, P.O. Box 67839-00200, Nairobi.
(b) Principal Secretary, Ministry of Environment and Mineral
Resources, NHIF Building, Community, P.O. Box 30521, Nairobi.
(c) County Director of Environment, Uasin Gishu County.
The National Environment Management Authority invites members of the public to submit oral or written comments within thirty (30) days from the date of publication of this notice to the
Director-General, NEMA, to assist the Authority in the decision making process of the plan.
GEOFFREY WAHUNGU, Director-General, MR/5353106
National Environment Management Authority.
Dated the 19th October, 2018.
GEOFFREY WAHUNGU,
Director-General, National Environment Management Authority.
Extracted Entities (1)
previous_gazette_ref
10687
Details
- Act / Legislation
- THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
- Reference
- No. 8 of 1999
- Signed By
- GEOFFREY WAHUNGU
- Title
- Director-General, National Environment Management Authority
- Ministry
- Ministry of Environment And Mineral
- Date Signed
- 19th October 2018
- Page
- 54
- Extraction Method
- regex
Source Gazette
Vol. CXX No. 125
Published 7th February 2018