GAZETTE NOTICE NO. 2524
GAZETTE NOTICE NO. 2524
THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
(No. 8 of 1999)
REGULATION
Pursuant to Regulation 21 of the Environmental Management, and
Co-ordination (Impact Assessment and Audit) Regulations, 2003, the
15th March, 2019 THE KENYA GAZETTE 1065
National Environment Management Authority (NEMA) has received an
Environmental Impact Assessment Study Report for the above proposed project.
The proponent, ACME Wanji Investments Limited, is proposing to construct three blocks (further divided into six blocks) of thirteen {13, (ground + 12)} floors comprising of one hundred and eighty one (181) housing units, 126 basement parking bays and 58 ground floor parking bays; the ground floor will also have 28No. residential units, walkways, green areas, swimming pool, gym area, caretakers's office and store and drive ways; typical 1st to 12th floors will comprise; Block 1 will have 24No. three (3) bedroom residential units with a detached servant's quarter (DSQ) for each; block 2 will have. 36No. three (3) bedroom units; Block 3 and 4 will have 48No. three bedroom units with a DSQ and a balcony; block 5 and 6 will comprise 48No. three (3) bedroom units with DSQ and 2 balconies, on plot L.R. No. 27253/68 in Syokimau area, Movoko Sub-County, Machakos County.
The following are the anticipated impacts and proposed mitigation measures:.
Impacts
Proposed Mitigation Measures
Soil erosion
• Implement soil erosion control measures and compact soil in open areas.
Effluent discharge
• Provide a sewer connection line to
MAVWASCO sewer line.
• Monitor effluent quality regularly to ensure that the stipulated discharge rules and standards are not Violated.
• ensure that no waste water is discharged directly into the immediate environment.
, • Ensure that convenience facilities are adequate for all the emplqyees on site and are cleaned on a daily basis.
Increased energy
• Advocating for the use of other renewable use sources of energy such as wind and solar energy, install solar panels.
• Use of clean fuels e.g. unleaded and de- sulphurized fuels in vehicles.
• Paving should only be carried out where necessary to reduce the reflection of the solar radiations.
• Using sustainable drainage systems that mimic the natural percolation Of water into the soil, and green roofs where possible.
Noise pollution-
• Ensure that construction machinery are kept in good condition through regular servicing and maintenance to reduce the amount of noise generated during use.
• All construction activities must be limited to between 8 a.m. and 5 p.m. during weekdays.
• ,No heavy construction activities/ noise generating activities shall be undertaken on
Sundays and public holidays.
• No construction activities shall be carried out on site at night;
• No blasting of stones if any shall be carried out within the project without prior notice being issued.
• Comply with EMCA (Noise and Excessive
Vibration Pollution Control) Regulations
2009.
• Ensure that all workers are provided with and wear PPE at all times.
• Ensure use of suppressors or noise shields on noisy.equipment.
Solid waste • Waste minimization by avoiding generation unsustainable construction practices.
Impacts
Proposed Mitigation Measures
• Provision of waste collection bins and cubicles for collection and temporal holding of the generated waste within the site before disposal.
• Provide solid waste handling containers within the project site to help in proper collection and management.
• Contract a registered and licensed waste collection company to assist in the disposal of the generated and collected solid waste to the County's designated final disposal she., • Ensure separation at source of the solid waste generated on site is done to enhance reusing of any material recovery.
Increased , water • Sensitize construction workers dh the demand importance of proper water management.
• Replace or repair leaking pipes supplying water to the construction sites to minimized wastage from`leakages or pipe burst.
• Ensure provision of adequate water storage facilities on the construction site to meet project needs during periods of high demand exterually and refill of storage tanks during periods of low demand.
• Reuse of waste water from the construction activities for curing of concrete surfaces and cleaning of equipment so as to reduce on the fresh water use.
• Direct construction water run-off to areas where it can soak into the ground or be collected and reused.
• Lock water tank valves to prevent unauthorized use and discourage wasteful use of water by construction workers.
• Repair water equipment as needed to prevent unintended discharges. Equipment such as water trucks and water reservoirs need to be inspected on a regular basis and incase of damage or fault, repairs should, be undertaken immediately.
• Install smart water meters and showers with
Infra-red Radiation sensors to control water use during occupation.
Air pollution • Avoid excavation works in extremely dry weather when soil is pulverized.
• ,Ensure all trucks delivering construction materials such as sand or those transporting wastes are properly covered to prevent the spread of dust.
• Ensure proper planning of transportation of materials to ensure that vehicle fills are increased in order to reduce the number of trips done per vehicle.
• Provide adequate personal protective gears to all employees.
• Ensure all .transportation trucks are covered while carrying away excavated soils and construction debris for final disposal.
' • Trucks bringing in construction materials should be used to ferry away any returnable to the supplier.
Occupational health • Provide adequate well stocked first aid and safety boxes across the site and adequately train all staff on basic firsi aid administration.
Impacts Proposed Mitigation Measures
• Adequate warning/inductions and instruction signs must be prominently displayed on the project site.
• Ensure that workers at the site are adequately protected through provision of suitable personal protective gears.
• Limit public access to the construction site.
• Ensure that all construction machines/ equipment are operated by experienced personnel and regularly serviced in order to avoid any accidents.
Fire • Smoking on site or burning of waste should be prohibited so as to reduce the source of ignition at the site.
• Electrical works such as electrical wiring should be done by qualified technicians or engineers.
• Place portable fire extinguishers at suitable locations.
• Train and induct workers on the use of fire extinguishers and other fire-fighting equipment.
• Designate a fire assembly point.
• Ensure fire safety warnings are prominently displayed at appropriate locations where fires are likely to occur.
The full report of the proposed project is available for inspection during working hours at:
(a) Director-General, NEMA, Popo Road, off Mombasa Road, P.O. Box 67839-00200, Nairobi.
(b) Principal Secretary, Ministry of Environment and Forestry, NHIF Building, Community, P.O. Box 30126-00100, Nairobi.
County Director of Environment, Machakos County.
The National Environment Management Authority invites members of the public to submit oral or written comments within thirty (30) days from the date of publication of this notice to the Director-General, NEMA, to assist the Authority in the decision making process of the plan.
GEOFFREY WAHUNGU, Director-General, MR/6019913 National Environment Management Authority.
Dated the 15th March, 2019.
GEOFFREY WAHUNGU,
Director-General, National Environment Management Authority.
Extracted Entities (1)
previous_gazette_ref
2524
Details
- Act / Legislation
- THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
- Reference
- No. 8 of 1999
- Signed By
- GEOFFREY WAHUNGU
- Title
- Director-General, National Environment Management Authority
- Ministry
- Ministry of Environment And Forestry
- Date Signed
- 15th March 2019
- Page
- 42
- Extraction Method
- regex
Source Gazette
Vol. CXXI No. 32
Published 28th January 2019