GAZETTE NOTICE NO. 5839
GAZETTE NOTICE NO. 5839
THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
(No. 8 of 1999)
REGULATION
Pursuant to Regulation 21 of the Environmental Management and
Co-ordination (Impact Assessment and Audit) Regulations, 2003, the
National Environment Management Authority (NEMA) has received an Environmental Impact Assessment Study Report for the above proposed project.
The proponent, Kaminara Agencies Limited, is proposing to provide a facility that will offer solutions on safe disposal of asbestos from various entities that intend to dispose-off the asbestos roofings within the coastal region. The proposed site is located at Mwawesa about 18 kilometers from Kaloleni Town and approximately 10 km off
Mombasa Road in Kaloleni Division, Kaloleni Constituency, Kilifi
County.
The following are the anticipated impacts and proposed mitigation measures:
Impacts
Proposed Mitigation Measures
Air quality
• Air monitoring should be done continuously in areas related to asbestos removal works.
Affected flora and • Preserve as possible indigenous trees and fauna other surrounding vegetation that need not be removed.
Cleanliness of • Workplaces are maintained in a clean state premises and plant and are free of asbestos waste.
Solid waste • Inform cleaning and disposal workers of their responsibilities in terms of the EMP.
• Ensure that all waste removal workers comply with the Waste Regulations of 2006.
• Collect waste paper generated at the work site in scrap paper bins.
Underground water • Construct a concrete lining in the asbestos contamination disposal site.
• The bottom to be at least 1 m above the sea level.
Temporary storage • Temporary site should be within the premises of asbestos material.
• Double wrap in 500 gauge or higher plastic sheet and label appropriately.
• Collect debris in sealed polythene woven bags or any other air tight containers.
• The bags should then be wrapped, into stacks for easy loading into transport vessels.
• Storage area must be restricted and secured on a 24 hour basis.
Management of
• Ensure management of temporary waste temporary waste storage sites is in line set procedures and storage sites legal requirements.
• Register and monitor waste volumes at the temporary waste storage site.
• Oversee the physical removal of the waste from the temporary waste storage sites.
Occupational health • Construction work will be limited to and safety daytime only.
• Workers to be adequately insured against accidents.
• All workers will be sensitized before construction begins on how to control accidents related to construction.
• Keep record of the public emergency service telephone numbers including: police, fire brigade, ambulance at strategic points.
• First aid kits at strategic places in the site.
• All workers to wear protective gear during construction e.g. helmets.
• Provide clean water and food to the workers on accident response.
Disposal scheduling .• The disposal and cleaning activities should and hours be limited from 7 am or sunrise (whichever is later) to 5 pm or sunset.
Post-disposal
• All transportation vessels and re-useable containers in contact with the asbestos waste shall be cleaned at the disposal site.
28th June, 2019 THE KENYA GAZETTE 2397
Impacts Proposed Mitigation Measures
• The disposal site should be maintained including the warning signs, the fence, and the gate to prevent vandalism and interference.
• Human activities which might interfere with the buried asbestos should not be allowed at the disposal site;
• The -waste generator shall notify the
Authority in writing on completion of disposal of asbestos Waste
The full report of the proposed project is available for inspection during working hours at:
(a) Director-General, NEMA, Popo Road, off Mombasa Road, P.O. Box 67839-00200, Nairobi.
(b) Principal Secnitary, Ministry of Environment and Forestry, NHIF Building, Community, P.O, Box 30126-00100, Nairobi.
(c) County Director of Environment, Kilifi County.
The National Environment Management Authority invites members of the public to submit oral or written comments within thirty (30) days from the date of publication of this notice to the
Director-General, NEMA, to assist the Authority in the decision making process of the plan.
GEOFFREY WAHUNGU, Director-General, -
MR/6335964 Nittional Environment Management Authority.
GAzErrE NOTICE No. 5840
THE ENVIRONMENTAL MANAGEMENT AND
CO-ORDINATION ACT
(No, 8 of 1999)
THE NATIONAL ENVIRONMENT MANAGEMENT
AUTHORITY
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT
FOR THE PROPOSED REFURBISHMENT AND EXPANSION OF
NYANZA GOLF COURSE INTO AN 18-HOLE GOLF COURSE
ON PLOT L.R.•NO. KISUMU MUNICIPALITY/BLOCK 2/16
ALONG KISUMU-BUSIA ROAD IN KISUMU CITY, KISUMU
COUNTY
•
INviTATION OF PUBLIC Comerrrs
Pursuant to Regulation 21 of the Environmental Management and
Co-ordination (Impact Assessment and Audit) Regulations, 2003, the
National Environment Management Authority (NEMA) has received an Environmental Impact Assessment Study Report for the above proposed project.
The proponent, Nyanza Golf Club Trustees, is proposing to refurbish and expand the golf course to a modern sports facility. The proposed project will comprise of the expansion from a 9No. holes to an 18No. golf course with a club house and irrigation equipment and other associated support facilities and amenities on plot L.R. No.
Kisumu Municipality/Block 2t16 along Kisumu-Busia Road in
Kisumu City, KiSumu County.
The following are the anticipated impacts and proposed mitigation measures:
Impacts Proposed Mitigation Measures
Air quality • Provision of dust masks to workers.
• Use labour intensive methods.
• Properly stack construction materials.
• Screen construction area.
• Stop work during strong winds.
• 'Water site to reduce dust emissions.
Noise and excessive • Operation during daylight hours only.
vibrations
• Provision of ear muffs to site workers.
Proposed Mitigation Measures
• Use noise barrier around the construction site Viz plywood, corrugated iron , sheets, blankets, etc.
• Place noisy equipment far from nearest noise receptor.
• Construction to be done only during the day.
• Sort out the waste from the source by providing easily identifiable waste receptors on site.
• Ensure a central transfer point for collection.
• Contract a registered waste collection agent.
• Adequate portable or permanent sanitation facilities serving all workers should be provided at the site.
Careful disposal Of waters from equipment washings into public sewer system.
• Ensure effective drainage into the septic tank.
• Regular maintenance checks on drainage system.
• Proper and constant maintenance of the premises plumbing system.
• Workers should be notified of sanitation requirements in the premises.
Storm water • Roof drainages installed and connected to management and street drains or collected into the water underground tank for use in cleaning, toilet conservation flushing and washing purposes.
•
• Installation of water meters to monitor amount used.
• Installation of water saving tap models.
Employ 24 hour trained security personnet guatd.
• Entrince and reception area of the building to be kept under 24-hour security guard.
• Acdess to premises controlled electronically.
Occupational health • Conform to all the requirements of the and safety Occupational Health and Safety Act, 2007.
• Erecting hazards warning signs along the access road.
▪ Reduced speed of delivery trucks.
• Provision of Personal Protective Equipment
• Signage erected at road turnings and at the
Pte.
Fine • First aid kits provided at easily accessible points.
• Smoke detectors installed to warn of fires.
• Install fire extinguishers at strategic points.
• Engage services of a safety officer.
• Provide fire assant:4y points.
• Ensure signs available directing building users to fire exits.
The full report of the proposed project is available for inspection during working hours at:
(a) Director-General, NEMA,a= Road, off Mombasa Road, (b) Principal Secretary, Ministry of Environment and Forestry, NHIF Building, Community, P.O. Box 30126-00100, Nairobi. • •
(c) County Director of Environment, Kisumu County.
Impacts
Solid waste
Liquid waste management
•
P.O. Box 67839-00200, N
The National Environment Management Authority invites members of the public to submit oral or written comments within thirty (30) days from the date of publication of this notice to the
Director-General, NEMA, to assist the Authority in the decision making process of the plan.
GEOFFREY WAHUNGU, Director-General, MR/6338028 National Environment Management Authority.
Dated the 28th June, 2019.
GEOFFREY WAHUNGU,
Director-General, National Environment Management Authority.
Extracted Entities (1)
previous_gazette_ref
5839
Details
- Act / Legislation
- THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
- Reference
- No. 8 of 1999
- Signed By
- GEOFFREY WAHUNGU
- Title
- Director-General, National Environment Management Authority
- Ministry
- Ministry of Environment And Forestry
- Date Signed
- 28th June 2019
- Page
- 34
- Extraction Method
- regex
Source Gazette
Vol. CXXI No. 82
Published 4th April 2019