Back
REGULATION 100% confidence via regex

GAZETTE NOTICE NO. 4224

GAZETTE NOTICE NO. 4224

THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT

(No. 8 of 1999)

REGULATION


Pursuant to regulation 21 of the Environmental Management and Co-ordination (Impact Assessment and Audit) Regulations, 2003, the National Environment Management Authority (NEMA) has received General Wastes Impacts Proposed Mitigation Measures • Identify sites with rare vegetation that may require protection; • Embark on planting trees and grassing and care for the same during construction. Soil Erosion • Any construction materials should be screened or covered to prevent off-site movement and surplus material should be removed from site to an approved disposal site; • Striping of vegetation should be limited to areas where civil works will be undertaken; • Berming of open trenches to prevent them from being washed away by runoff; • Provision of channels and anti-scour pads especially in steep slopes • Plant grass and trees along verges and embankments; • Dispose of the storm water through appropriate drains and inspect at regular intervals; • Control earthworks; • Dispose of excess excavated soil appropriately; • Use excess soil to recondition material sites. Noise and vibration • Construction and use of construction machinery should be limited between 0600 hrs and 1800 hrs; • The contractor should use modern equipment which produces the least noise possible; • Any unavoidable noisy equipment should be identified and located in an area where it has least impact; • Noise shielding screens should be used and the operation of such machinery restricted to when it is actually required. Health and safety effects • The contractor shall comply with all standards and legally required health and safety regulations as promulgated under the occupational Health and safety Act of 2007 and associated regulations; Proposed Mitigation Measures • Accidental fires will be reported to emergency teams, as well as control with appropriate equipment and properly documented; • Ensure that there is basic fire-fighting equipment is available on site as per the requirement of the local emergency services. • Storm water drains in the area should be routinely inspected by the environmental officer for any solid waste accumulation to avoid blockages and associated problems; • The contractor shall ensure that any liquid waste generated during decommissioning is disposed to a proper stabilizing lagoon. • Clearing of bushes, excavation and cutting should be restricted within the project area; • All solid waste to be collected at a central location at each site and will be stored temporarily until removal to an appropriate permitted land fill site; • No dumping within the surrounding areas is to be permitted; • Where potentially hazardous substances are being disposed of, a chain of custody should be kept with the register as a proof of final disposal; • Waste generated at the site should be sorted by the contractor and disposed of in a suitable manner into different waste streams, whenever possible recycling should carried out; • Litter generated by the construction crew must be collected in rubbish bins and disposed of weekly at registered waste disposal sites. • • Discharge of leachate from the dumpsite must be properly contained for treatment and disposal; • The leachate should be analyzed regularly to determine the chemical composition, this will inform the threshold of treatment needed; • Leachate should never be released into the sewer system, storm drain and river before proper treatment. Impacts Fire outbreaks Liquid Wastes Leachate formation Methane /hydrogen • The contractor must provide and maintain personal protective equipment and facilities to employees working with hazardous chemical substances; • Official training in the correct fit, use, care, storage and limitation of personal protective clothing (PPEs), respiratory and hearing equipment must be given to the employees; • The site workers should be trained on basic first aid methods. Ventilation pipes be fitted with gas taps • sulphide and other gas and flares should be installed. management The full report of the proposed project is available for inspection during working hours at: (d) Principal Secretary, Ministry of Environment and Forestry, NHIF Building, Community, P.O. Box 30126-00100, Nairobi. (e) Director-General, NEMA, Popo Road, off Mombasa Road, P.O. Box 67839-00200, Nairobi. (f) County Director of Environment, Kajiado County. 19th June, 2020 A copy of the report can be downloaded at www.nema.go.ke The National Environment Management Authority invites members of the public to submit oral or written comments within thirty (30) days from the date of publication of this notice to the Director-General, NEMA, to assist the Authority in the decision making process regarding this plan. Comments can also be emailed to dgnema@nema.go.ke Owner Make Chassis No. Location Apex Systems Consulting Group Limited Toyota Prado KZJ95 - 0066047 Toyotsu Auto Mart Kenya Limited, Popo Road, South C Nairobi P.O. Box 100974- 00101, Nairobi Dated the 2nd June, 2020. GUILLAUME GRANIER, Chief Operating Officer, MR/0763388 Toyotsu Auto Mart (K) Limited MAMO B. MAMO, Ag. Director-General, MR/0781653 National Environment Management Authority.

Dated the 2nd June, 2020.

GUILLAUME GRANIER,

Chief Operating Officer, Toyotsu Auto Mart (K) Limited.

Extracted Entities (1)

previous_gazette_ref

4224

Details

Act / Legislation
THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
Reference
No. 8 of 1999
Signed By
GUILLAUME GRANIER
Title
Chief Operating Officer, Toyotsu Auto Mart (K) Limited
Date Signed
2nd June 2020
Page
35
Extraction Method
regex