GAZETTE NOTICE NO. 2315
GAZETTE NOTICE NO. 2315
THE WATER ACT
(No. 43 of 2016)
APPROVAL
in accordance to the requirements of section 139 of the Water Act, 2016.
THE KENYA GAZETTE 13th March, 2020
1324 1324
After considering the application, the written and oral submissions by all stakeholders during the consultation period, and based on latest available data, WASREB has determined an upward tariff review for ELDOWAS is justified in order to improve service delivery, operate sustainably and protect consumer interests by meeting the tariff conditions attached to the tariff.
WASREB gives a one (1) month’s notice to all existing and potential customers of ELDOWAS that the approved tariffs for the five financial years, 2019/20, 2020/21, 2021/22, 2022/23 and 2023/24 shall be as follows:
1.0 Approved Tariff
1.1 Water Tariff Structure for the period 2019/2020 to 2023/2024
Customer Category Approved
Domestic Consumption Block in m³ Tariff
1-6. 35
7-20. 45
21-50 68
51-100 75
101-300 94
>300 105
Multi-dwelling units/gated communities 45
Commercial/industrial/government
1-50 68
51-100 75
101-300 94
>300 105
Public schools, universities and colleges
0-600 30
601 - 1200. 35
>1200 45
Water kiosk (per m3) 35
1.2 Sewerage Tariff
(a) Consumers with a Water Connection
The volume of sewerage to be charged shall be determined at 75% of the volume of water consumed at the rates specified as follows
Customer Category Approved
Domestic Consumption Block in m³ (75 % of water consumed) Tariff Per M3
1-6. 30
7-20. 35
21-50 50
51-100 55
101-300 60
>300 65
Multi-dwelling units/gated communities
Commercial/industrial/ government
1-50 50
51-100 55
101-300 60
>300 65
Public schools, universities and colleges
1-600 30
601 - 1200. 35
>1200 45
(b) Consumers without a Water Connection
Sewerage consumers without a water connection shall be charged as follows:
• Domestic (per single dwelling unit): KSh. 300 per month
• All other categories: 75% of the volume of water consumed at the rates specified in 3 (a) above
1.3 Indexation of the Approved Tariff
The utility’s approved tariffs for water and sewerage shall be eligible for annual indexation, as per the regulations of the Water Services
Regulatory Board (WASREB). The inflation adjustment shall come into effect every July of the tariff period commencing July 2021.
1.4 Miscellaneous Charges
Item/ Service Charge (KSh.)
Standing Charge per Connection per Month
Connection Size
½ inches 50
¾ inches 100
1 inch 250
13th March, 2020 THE KENYA GAZETTE
Item/ Service Charge (KSh.)
1 ½ inches 250
2 inches 250
3 inches 450
4 inches 800
6 inches 1250
8 and above 2000
Water Deposit
Category of Consumer
Domestic 2500
Retail shops less than 10m3 3000
Retail shops more than 10m3 3,500
Bar, restaurants less than 15 m3 4000
Bar, restaurants more than 15 m3 6,000
Hotel class “A” and “B” less than 150 m3 12,000
Hotel class “A” and “B” more than 150 m3 15000
Hotel class “C” and ‘D’ less than 150 m3 18000
Hotel class “C” and ‘D’ more than 150 m3 20,000
Hospitals more than 150 m3 20,000
Health centres less than 150 m3 12,000
Schools and other institutions more than 200 m3 20,000
Schools less than 200 m3 10,000
Minor construction sites more than 200 m3 15,000
Major construction sites more than 300 m3 50,000
Light industries less than 200 m3 30,000
Medium industrial between 200 m3 and 300 m3 50,000
Heavy industries more than 300 m3 100,000
Water kiosks 5,000
Customers with sewer only connection to be charged a deposit equivalent to water connection
Other Charges
Service
New water connection fee – Connection size: ½ inch to 1 inch 2,500
New water connection fee – Connection size: 1.5 inches to 3 inches 7,500
New water connection fee – Connection size above 3inches 15,000
Water reconnection fee – at meter point 1,000
Water reconnection fee – at mains 5,000 and double deposit
Tanker –78000, 18,000 litres 2,500 and 6,000 respectively per tanker within
ELDOWAS area for all consumers
Sale of water per m3 at bowsing point (own tanker) 75
Replacement of stolen or damaged meters 100% of the market cost of the meter
Meter testing on request 500
Sewer connection, residential/domestic 5,000
Sewer connection, commercial, government, schools, universities and colleges 7,500
Sewer connection, Industrial 15,000
Private sewer unblocking 2,500
Leak detection services 1,000
Sewer reconnection fee 15,000
Statement of account fees 200
For cutting off the supply at the request of the consumer 200
For turning on the supply otherwise than in respect of a first connection 200
Exhauster services (company exhauster) 5,000 for other customers and 4,000 for informal settlements
Private exhausters (dumping into the company’s sewer system) 15,000 per truck per month
Sale of sludge 300 per tonne
Penalties
Illegal water connection, (fraud), commercial, industry, construction 100,000 plus estimated consumption during the period of the illegality
Illegal water connection, (fraud) – Domestic 30,000 plus estimated consumption during the period of the illegality
Overcharging (fraud) at water kiosk 30,000
Illegal sewer connection (fraud), commercial, industry, construction 100,000
Illegal sewer connection (fraud), domestic, government, schools, universities and colleges 30,000
Self-reconnection after cut off for non-payment 30,000 and billing to be backdated from date of cut off
Surcharge for tampering with meters (this to include meter removal, reversing of meter etc) 30,000
Unauthorized sale of water 15,000
Surcharge for direct suction of water from the supply line using a pump 30,000
2.0 Approved Cost Structure
Below is the summary of the projected annual cost structure that makes up the total costs to be incurred by ELDOWAS during the tariff period:
THE KENYA GAZETTE 13th March, 2020
1326 1326
(KSh.) (KSh.)
Cost Subject to Annual Indexation
Operations and Maintenance costs 767,243,187
Fixed Costs
Average Annual Investment Cost 145,450,766
Debt 64,278,006
Average Annual Asset Renewal 89,694,151
Sub Total- Fixed Costs 299,622,924
Total Average Annual Cost 1,066,666,111
Projected Average Annual revenue 1,153,975,490
Average Annual Cost Coverage 108%
3.0 Conditions attached to the tariff approval
The tariff adjustment approval is approved for five years and during which all the assumptions made in the tariff projections will be monitored.
The conditions attached to this approval which shall form part of the license conditions of Eldoret Water and Sanitation Company are:
(i) Service Delivery Conditions attached to the Tariff
Target 2019/20 2020/21 2021/22 2022/23 2023/24
Water coverage 74% 76% 78% 80% 82%
Sewerage coverage 31% 34% 38% 41% 45%
Water quality standards 92% 100% compliance with the quality standards
Non- Revenue Water 32% 27% 25% 24% 23%
Hours of Supply (Hrs) 15 15 15 15 15
Personnel Expenditure as % of O&M costs 46% 42% 38% 34% 30%
Staff per 1000 connections 4 4 4 4 4
Metering ratio 100% 100% 100% 100% 100%
Collection efficiency 95% 95% 95% 95% 95%
Resale at kiosk Regulate resale by kiosk vendors at KSh. 2 per 20-litres. Tariffs at kiosks must be displayed at strategic points for public awareness
(i) Annual budgets: The WSP shall adhere to the budgetary levels set in the tariff.
(ii) Surpluses: The surpluses projected to be realised shall be set aside to implement priority service delivery capital projects. ELDOWAS shall be required at the end of every financial year to identify the priority project to be implemented and obtain approval from WASREB.
(iii) Reporting: The utility shall submit to WASREB a quarterly performance report.
(iv) Catchment Protection: The utility shall undertake measures to conserve/ protect the catchment areas of their source of water as part of
Corporate Social Responsibility.
(v) Investments: The utility shall undertake the following investments:
Plant/Station Description
2019-2020 2020-2021 2021-2022 2022-2023 2023-2024
(KSh.) (KSh.) (KSh.) (KSh.) (KSh.)
Moiben Dam Fencing of the dam 3,000,000
Two Rivers Dam Fencing of the dam 1,000,000 Ellegrini Dam Fencing of the dam 1,000,000
Sosiani Treatment
Replacement of air scour blower 2,500,000 Purchase of 77 KVA standby electric generator 2,500,000
Augmentation of the community line rising main 5,000,000
Installation of a new prosonic sensor 500,000
Installation of flow measuring devices from the treatment works complete with housing 1,000,000
Boundary Treatment
Auto manual step screen 14,000,000 Installation of a new prosonic sensor 500,000 installation of flow measuring devices from the treatment works complete with housing 1,000,000
Kesses Installation of solar system 13,000,000 10,000,000
Lab Equipment Purchase of atomic absorption spectrophotometer 4,500,000
Motor Vehicles and other Motorized equipment
Double cab pick ups 5,000,000 10,000,000 5,000,000 5,000,000 5,000,000
Purchase of wheeled backhoe (excavator) 10,000,000 Purchase of jet canon lorry 30,000,000
Headquarters and area
Offices Central stores construction 5,000,000
POE network switches 100,000 200,000
Centralized and service are printers 580,000 580,000
Smoke detectors for HQ and disaster recovery site 2,000,000
Total 18,600,000 24,780,000 31,580,000 24,500,000 38,500,000
13th March, 2020 THE KENYA GAZETTE
Water Pipeline Extensions Amount (KSh.)
Total
2019-2020 Sogomo 2,585,253
Kipkenyo 1,901,412
Kapsaret 7,182,016
Total 11,668,681
2020-2021 Annex 2,051,436
Kpa 2,339,902
Kuinet 2,432,302
Chepkanga 2,525,626
Kesses 4,105,280
Total 13,454,546
2021-2022 Kiplombe 5,666,439
Langas 5,418,417
Total 11,084,855
2022-2023 Dutch Tank Kiburgei Chief’s Office 938,902
Kesses Moi University 5,979,529
Kipkorgot A 8,272,386
Total 15,190,817
2023-2024 Kipkorgot B 7,838,767
Kokwos 4,727,041
Total 12,565,809
Year Sewerage Extensions Amount (KSh.)
Total
2019-2020 Ngurunga 21,049,024
Main Trunk MT6 27,411,056
Total 48,460,079
2021-2022 Annex Sewer Line 18,365,468
Shauri Havard 16,707,281
Prison P10 2,275,419
Huruma H15 24,932,216
Total 62,280,384
2021-2022 Upper Elgon View 18,670,432
Kidiwa 58,182,641
Total 76,853,073
2022-2023 Huruma 19,101,720
Elgon View Ev13A 8,440,506
Elgon View Ev13B 7,583,857
Kamukunji Extensions Km16 37,512,151
Total 72,638,234
2023-2024 Kipkorgot Area 19,270,152
Mwanzo Mz11 78,546,235
Total 97,816,387
Date the 27th February, 2020.
ROBERT GAKUBIA, Chief Executive Officer, MR/0769452 Water Services Regulatory Board.
Dated the 27th February, 2020.
ROBERT GAKUBIA,
Chief Executive Officer, Water Services Regulatory Board.
Extracted Entities (1)
previous_gazette_ref
2315
Details
- Act / Legislation
- THE WATER ACT
- Reference
- No. 43 of 2016
- Section
- section 72 (1) (b)
- Signed By
- ROBERT GAKUBIA
- Title
- Chief Executive Officer, Water Services Regulatory Board
- Date Signed
- 27th February 2020
- Page
- 29
- Extraction Method
- regex
Source Gazette
Vol. CXXII No. 49